Type:
|
Contract
|
Status:
|
Agenda Ready
|
|
On agenda:
|
4/15/2026
|
Final action:
|
|
|
Title:
|
AUTHORIZE the Chief Executive Officer (CEO) to:
A. EXECUTE Modification No. 10 to Contract No. AE333410011375 with Parsons Transportation Group, Inc. (PTG) to provide additional professional services needed to complete the environmental phase of the I-605 Corridor Multimodal Improvements Project (I-605 CMIP) in the amount of $21,826,798, increasing the total contract value from $28,723,699 to $50,550,497 and, extend the period of performance from September 30, 2026, to December 30, 2028; and
B. EXECUTE Modification No. 10 to Contract No. AE5204200 with HDR Engineering, Inc. (HDR) to provide additional professional services that are needed to complete the environmental phase of the I-605 CMIP in the amount of $25,108,331, increasing the total contract value from $38,559,071 to $63,667,402 and extend the period of performance from September 30, 2026, to December 30, 2028.
|
|
Indexes:
|
"Hot Spots" Program, Budgeting, Complete streets, Construction, Contract administration, Contracts, Environmental Impact Report, Environmental impact statements, Grant Aid, High occupancy vehicle lanes, I-5, I-605, I-605/Sr-60 Interchange Improvements (Project), Interchange Improvements (Project), Interchanges, Local transportation, Measure M, Measure R, Motion / Motion Response, Multimodal, National Environmental Policy Act Of 1969, Outreach, Procurement, Professional Services, Project, Project management, Ramps (Interchanges), Safety, Southern California Highways, SR-60, Strategic planning, Transportation system management, Travel demand management
|
Meeting_Body PLANNING AND PROGRAMMING COMMITTEE APRIL 15, 2026 Subject SUBJECT: I-605 CORRIDOR MULTIMODAL IMPROVEMENTS PROJECT Action ACTION: APPROVE RECOMMENDATION Heading RECOMMENDATION Title AUTHORIZE the Chief Executive Officer (CEO) to: A. EXECUTE Modification No. 10 to Contract No. AE333410011375 with Parsons Transportation Group, Inc. (PTG) to provide additional professional services needed to complete the environmental phase of the I-605 Corridor Multimodal Improvements Project (I-605 CMIP) in the amount of $21,826,798, increasing the total contract value from $28,723,699 to $50,550,497 and, extend the period of performance from September 30, 2026, to December 30, 2028; and B. EXECUTE Modification No. 10 to Contract No. AE5204200 with HDR Engineering, Inc. (HDR) to provide additional professional services that are needed to complete the environmental phase of the I-605 CMIP in the amount of $25,108,331, increasing the total contract value from $38,559,071 to $63,667,402 and extend the period of performance from September 30, 2026, to December 30, 2028. Issue ISSUE At the January 2025 meeting, the Board approved staff's request to reinitiate work on the Project Approval and Environmental Documents (PAED) phase of the I-605 CMIP, consistent with the I-605 Corridor Improvements Project (CIP). Accordingly, both contracts that support the I-605 CMIP must be modified to update, revise, and complete the technical studies that support the Environmental Impact Report/Environmental Impact Statement (EIR/EIS) in alignment with the Board Motion 42 (Attachment A), which was introduced on October 22, 2020, by Directors Solis, Hahn, Garcia, Fasana, Garcetti, and Bonin. The contract modifications include the development of locally supported alternatives that minimize right-of-way impacts and include complete streets and multimodal improvements. Background BACKGROUND The current scope of the I-605 CMIP is the result of Metro and Caltrans combining t... Click here for full text
|