File #: 2025-0321   
Type: Program Status: Agenda Ready
File created: 4/17/2025 In control: Planning and Programming Committee
On agenda: 6/18/2025 Final action:
Title: CONSIDER:? ? A. APPROVING $12,519,439 in additional programming within the capacity of Measure R Multimodal Highway Subregional Programs and funding changes via the updated project list shown in Attachment A. Projects within this Measure R Multimodal Highway Subregional Program include traffic signal, pedestrian, bicycle, transit, and roadway improvements; ? B. APPROVING the deobligation of $4,140,439 in previously approved Measure R Multimodal Highway Subregional Program funds to re-allocate said funds to other existing Board-approved Measure R Projects as shown in Attachment A; and?? ? C. AUTHORIZING the Chief Executive Officer (CEO) or her designee to negotiate and execute all necessary agreements for Board-approved Projects.??
Sponsors: Program Management (Department), Maria Luk
Indexes: "Hot Spots" Program, 405 110 105 Sr91 Ramp&Interch (Project), Accessibility, Agreements, Arroyo Verdugo subregion, Audit, Bell Gardens, Bicycling, Bids, Budgeting, Burbank, Bus rapid transit, Call For Projects, Capital Project, Carson, City of Los Angeles, Complete streets, Construction, Contractors, Curbs, Eb Sr91 Atlantic Avenue /Cherry Avenue Auxiliary Lane Improvement (Project), El Segundo, Funding plan, Gardena, Gateway Cities (Southeast LA County) Service Sector, Gateway Cities subregion, Glendale, Grant Aid, Guidelines, Hawthorne, Highway Operational Improvements In Arroyo Verdugo Subregion (Project), Hwy Opr Imp Virgenes/Malibu (Project), I-105, I-110, I-405, I-5, I-605, I-605 Beverly Interchange Imp (Project), I-605 Corridor "Hot Spot" (Project), I-605 Hot Spots- Wb (Westbound) Sr-91 Improvements From Alondra To Shoemaker (Project), I-605/Sr-60 Interchange Improvements (Project), I-605/Valley Blvd Interchange Improvement Project (Project), I-710, I710 South Early Action Project (Project), Information systems, Interchange Improvements (Project), Intersections, Lancaster, Las Virgenes-Malibu Council of Governments, Las Virgenes/Malibu subregion, Los Angeles County Information Exchange Network, Metro Affordable Transit Connected Housing Program, Multimodal, Palmdale, Pedestrian safety, Pedestrians, Plan, Professional Services, Program, Project, Ramps (Interchanges), Regional Surface Transportation Improvements, Safety, Santa Fe Springs, Sidewalks, Signal head, South Bay Cities subregion, Southern California Highways, Sr-138 Capacity Enhancements - Additional Segments (Project), Sr-91 Acacia Court To Central Avenue Improvement Project (Project), Strategic planning, Striping, Subsidies, Sustainable transportation, Traffic control, Traffic flow, Traffic signals, Transit traffic, Travel time, Turning lanes, Unit costs, Vehicle design, Vehicle miles of travel, Visibility, Volume, Whittier
Attachments: 1. Attachment A - Measure R Multimodal Hwy Subregional Programs June 2025, 2. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
JUNE 18, 2025

Subject
SUBJECT: MEASURE R MULTIMODAL HIGHWAY SUBREGIONAL PROGRAMS - SEMI-ANNUAL UPDATE

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
CONSIDER:?
?
A. APPROVING $12,519,439 in additional programming within the capacity of Measure R Multimodal Highway Subregional Programs and funding changes via the updated project list shown in Attachment A. Projects within this Measure R Multimodal Highway Subregional Program include traffic signal, pedestrian, bicycle, transit, and roadway improvements;
?
B. APPROVING the deobligation of $4,140,439 in previously approved Measure R Multimodal Highway Subregional Program funds to re-allocate said funds to other existing Board-approved Measure R Projects as shown in Attachment A; and??
?
C. AUTHORIZING the Chief Executive Officer (CEO) or her designee to negotiate and execute all necessary agreements for Board-approved Projects.??

Issue
ISSUE

The Measure R Multimodal Subregional Programs Semi-Annual Update reports on subregional project priorities that have been revised and budgets that need to be amended to implement the Measure R multimodal subregional projects.
?
The updated project list (Attachment A) reflects (1) new projects, (2) projects that have received prior Board approval, and (3) proposed changes related to schedules, scope, and funding allocations for existing projects. The Board's approval is required as the updated project list serves as the basis for Metro to enter into agreements with the respective implementing agencies. ?

Background
BACKGROUND

The Measure R Expenditure Plan allocates funding to projects under the multimodal highway operational improvement subfund program as listed in Attachment A. Metro staff works closely with the local jurisdictions and subregions on project eligibility reviews of the proposed projects for this update. When capacity at the local level is lim...

Click here for full text