Title: AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 4 to Contract No. PS46172000, with Gannett Fleming Transit & Rail Systems, for engineering support of rail maintenance to exercise the first-year option, for an amount of $5,000,000, increasing the total contract not-to-exceed amount from $16,000,000 to $21,000,000, through April 2021.
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Board approved Contract, Budgeting, Capital Project, Capital Project Funds, Contracts, Disadvantaged business enterprises, Maintenance, Maintenance of way, Operations and Maintenance, Procurement, Professional Services, Rail transit, Safety, State Of Good Repair, Strategic planning, Transit System
Attachments: 1. Attachment A - List of Supported Project Uses, 2. Attachment B - Procurement Summary, 3. Attachment C - Contract Modification Change Order Log, 4. Attachment D - DEOD Summary
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
NOVEMBER 21, 2019

Subject
SUBJECT: ENGINEERING SUPPORT FOR RAIL MAINTENANCE SERVICES

Action
ACTION: APPROVE CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 4 to Contract No. PS46172000, with Gannett Fleming Transit & Rail Systems, for engineering support of rail maintenance to exercise the first-year option, for an amount of $5,000,000, increasing the total contract not-to-exceed amount from $16,000,000 to $21,000,000, through April 2021.

Issue
ISSUE

Metro Maintenance and Engineering has limited scope and depth of engineering and technical resources to develop and execute capital projects and meet the day-to-day engineering needs necessary to maintain and improve railway infrastructure assets and systems. Contract No. PS46172000 has been providing significant engineering support that's enabled Metro to augment internal resources on an on-call basis in situations where either Metro does not have sufficient capacity or the expertise necessary to perform a task.

The base term for Contract No. PS46172000 is approaching its initial contract authority. A contract modification is required to exercise the first-year option to continue providing engineering support.

Background
BACKGROUND

In April 2018, the Board of Directors approved the award of Contract No. PS46172000 for Rail Maintenance and Engineering support in a total not-to exceed amount of $31,000,000, inclusive of $16,000,000 for the initial two-year base, and $5,000,000 for each of the three, one-year options. This task order based contract provides for a range of services that includes train control, traction power, communications, track, mechanical, electrical, plumbing, civil design, and fare collection. Also included are support services for project management, construction management, and computer aided design and drafting (CADD).