Meeting_Body
FINANCE, BUDGET, AND AUDIT COMMITTEE
NOVEMBER 19, 2026
Subject
SUBJECT: WESTSIDE PURPLE LINE EXTENSION SECTION 2
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
AMEND the Life-of-Project (LOP) budget for the Westside Purple (D) Line Extension Section 2 Project (Project) by $296,000,000 from $2,574,969,299 to $2,870,969,299 using the fund sources as summarized in Attachment A and consistent with the provisions of the Board-adopted Measure R and Measure M Unified Cost Management Policy (Attachment B).
Issue
ISSUE
The Project is in its ninth year of construction and is 95% complete as of September 2026. To date, the Project has experienced unexpected conditions and unanticipated additional cost obligations that have drawn down the Project Contingency below the 3% Project reserve threshold which means there may be insufficient funds to cover the remaining costs required for Project completion.
The LOP budget increase request accounts for costs of settlement of a time-related claim that has been in negotiations with the Design-Build contractor, provides additional funding that is needed for additional construction costs, real estate, and professional services impacted by schedule delays, and provides contingency to account for potential future impacts and risks to the Project.
Background
BACKGROUND
The Project is the second of three sections of the nine-mile Purple (D) Line Extension. The Project runs westward from the recently opened Wilshire/La Cienega Station (that is part of the Section 1 Project) through Beverly Hills to Century City. The Project is located entirely underground, primarily following Wilshire Boulevard, and includes the design and construction of approximately 2.59 miles of double-track heavy rail subway and two new stations, as well as the purchase of 20 heavy rail vehicles. The Beverly Dr Station is within the jurisdiction of the City of Beverly Hills, and the Century City Station is within t...