Title:
|
RECEIVE oral report on the Major Project Status by the Chief Program Management Officer.
|
Indexes:
|
1st Street Station, Arcadia, Barriers (Roads), Blue Line Improvement, Budgeting, Caverns, Century City, City of Los Angeles, Conductors (Trains), Construction, Contractors, Crenshaw/LAX Transit Corridor Project, Customer service, Downey, Elevators, Excavation and tunneling, Florence, Full Funding Grant Agreement, Grand Ave Arts/Bunker Hill Station, Historic Broadway Station, Hubs, Hyde Park, I-5, I-5 North Corridor, I-5 South Corridor, I-605, Lane closure, Little Tokyo/Arts District Station, Los Angeles International Airport, Maintenance, Metro Blue Line, Metro Crenshaw Line, Metro Exposition Line, Metro Gold Line, Metro Green Line, Metro Orange Line, Metro Purple Line, Metro Rail A Line, Metro Rail C Line, Metro Rail D Line, Metro Rail E Line, Metro Rail K Line, Metro Rail L Line, Metro Vision 2028 Plan, Norwalk, Oral Report / Presentation, Pasadena, Patsaouras Plaza Busway Station, Pedestrians, Program management, Project, Project management, Project Status Report, Regional Connector Transit Corridor Project, Santa Monica, Southern California Highways, SR-134, SR-170, Start of first construction, Test trains, Testing, Tunnel shafts, Twenty-eight by '28 Initiative, Westside Cities subregion, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3, Westside/Central Service Sector, Willowbrook/Rosa Parks Station
|
Attachments:
|
1. Presentation
|
Meeting_Body
CONSTRUCTION COMMITTEE
OCTOBER 17, 2019
Subject
SUBJECT: PROGRAM MANAGEMENT MAJOR PROJECT STATUS REPORT
Action
ACTION: ORAL REPORT
Heading
RECOMMENDATION
Title
RECEIVE oral report on the Major Project Status by the Chief Program Management Officer.
Discussion
DISCUSSION
Update report covering the month of October 2019 by the Chief Program Management Officer.
Attachments
ATTACHMENTS
Attachment A - Program Management Major Project Status Report
Prepared_by
Prepared by:
• Crenshaw/LAX - Sameh Ghaly, Sr EO Project Mgmt., (213) 418-3369
• Regional Connector - Gary Baker, EO Project Mgmt., (213) 893-7191
• Westside Purple Line Ext 1 - James Cohen, EO Project Mgmt., (213) 922-7911
• Westside Purple Line Ext 2 - Michael McKenna, EO Project Mgmt., (213) 312-3132
• Westside Purple Line Ext 3 - Kimberly Ong, EO Project Mgmt., (323) 903-4112
• Patsaouras Plaza Busway Station -Timothy Lindholm, Sr. EO Project Mgmt., (213) 922-7297
• Willowbrook/Rosa Park Station -Timothy Lindholm, Sr. EO Project Mgmt., (213) 922-7297
• The New Blue - Timothy Lindholm, Sr. EO Project Mgmt., (213) 922-7297
• I-210 Barrier Replacement - Androush Danielians, EO Project Engr., (213) 922-7598
• I-5 North - Abdollah Ansari, Sr EO Construction & Engr., (213) 922-4781
• I-5 South - Abdollah Ansari, Sr EO Construction & Engr., (213) 922-4781
• Presentation - Shannon Hanley, Chief Administrative Analyst, (213) 922-1350
|