Title: AUTHORIZE the Chief Executive Officer to: EXECUTE Modification No. 14 to Contract No. PS66773HRT with Sepulveda Transit Corridor Partners, LLC (STCP) to provide additional technical services in the amount of $29,645,334.25 for design and project development to advance the approved Sepulveda Transit Corridor Locally Preferred Alternative (LPA), increasing the contract value from $87,353,033.75 to $116,998,368; AUTHORIZE additional Contract Modification Authority (CMA) for Contract No. PS66773HRT in the amount of $2,964,533.43 and authorize the CEO to execute individual Contract Modifications within the Board-approved CMA; and AMEND the adopted FY27 budget to increase non-labor funding for Project #460305 by $26,500,000 from $59,023,199 to $85,523,199.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Change Order Log, 3. Attachment C - DEOD Summary, 4. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
EXECUTIVE MANAGEMENT COMMITTEE
NOVEMBER 19, 2026

Subject
SUBJECT: SEPULVEDA TRANSIT CORRIDOR

Action
ACTION: APPROVE RECOMMENDATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to:

EXECUTE Modification No. 14 to Contract No. PS66773HRT with Sepulveda Transit Corridor Partners, LLC (STCP) to provide additional technical services in the amount of $29,645,334.25 for design and project development to advance the approved Sepulveda Transit Corridor Locally Preferred Alternative (LPA), increasing the contract value from $87,353,033.75 to $116,998,368;

AUTHORIZE additional Contract Modification Authority (CMA) for Contract No. PS66773HRT in the amount of $2,964,533.43 and authorize the CEO to execute individual Contract Modifications within the Board-approved CMA; and

AMEND the adopted FY27 budget to increase non-labor funding for Project #460305 by $26,500,000 from $59,023,199 to $85,523,199.

Issue
ISSUE

At its January 2026 meeting, the Board selected the Locally Preferred Alternative (LPA) for the Sepulveda Transit Corridor as heavy rail transit underground between Van Nuys Metrolink Station and the E Line Expo/Sepulveda station modified to provide connections to the Metro G Line and East San Fernando Valley (ESFV) light rail line at Van Nuys Boulevard. The Sepulveda Transit Corridor is a Measure M and Metro Pillar Project. In addition, the Board authorized further design refinements and advancement of the LPA to address project cost, risk, and comments received on the Draft Environmental Impact Report (EIR).

Staff is seeking the Board’s approval of a contract modification to provide engineering and project development services to continue the advancement of the Project. This modification will allow staff to advance Project design up to approximately 30 percent level providing for more detailed project design to better understand and address project cost and risk. The contractor will also finalize the project...