File #: 2022-0485   
Type: Contract Status: Passed
File created: 7/14/2022 In control: Operations, Safety, and Customer Experience Committee
On agenda: 9/15/2022 Final action: 9/22/2022
Title: AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 7 to Contract No. PS46172000, with Gannett Fleming Transit & Rail Systems, for engineering support of transit infrastructure maintenance to increase the total contract not-to-exceed spending authority by $5,000,000 from $26,000,000 to $31,000,000.
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Bids, Board approved Contract, Budgeting, Capital Project, Capital Project Funds, Contracts, Maintenance, Procurement, Professional Services, Rail transit, Security, State Of Good Repair, Strategic planning, Surveys, Transit System, Transportation Development Act - Article 4, Transportation Development Act of 1971
Attachments: 1. Attachment A - List of Supported Project Uses, 2. Attachment B - Procurement Summary, 3. Attachment C - Contract Modification_Change Order Log, 4. Attachment D - List of Task Orders and Values, 5. Attachment E - DEOD Summary2
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
SEPTEMBER 15, 2022

Subject
SUBJECT: ENGINEERING SUPPORT FOR TRANSIT INFRASTRUCTURE MAINTENANCE

Action
ACTION: APPROVE CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 7 to Contract No. PS46172000, with Gannett Fleming Transit & Rail Systems, for engineering support of transit infrastructure maintenance to increase the total contract not-to-exceed spending authority by $5,000,000 from $26,000,000 to $31,000,000.

Issue
ISSUE

Contract No. PS46172000 has been providing key engineering support that enables Metro to augment internal resources on an on-call basis in situations where Metro lacks the capacity or expertise necessary to perform the required task. Staff is currently working on the re-procurement for these services and anticipates issuing a competitive solicitation in the next couple of months. A contract modification is required to increase the funding portion of the remaining contract term to continue providing engineering support through April 26, 2023.

Background
BACKGROUND

In April 2018, the Board of Directors approved the award of Contract No. PS46172000 for Maintenance and Engineering Department support in a total not-to-exceed amount of $31,000,000 ($16,000,000 for the initial two-year base period, and $15,000,000 for the three, one-year options at $5,000,000 per year). In December 2019, the Board approved exercising the first option year to increase the contract value from $16,000,000 to $21,000,000 and extended the performance period from April 27, 2020, to April 26, 2021. In March 2021, the Board approved exercising the second option year to increase the contract value from $21,000,000 to $26,000,000 and extend the performance period from April 27, 2021, to April 26, 2022. In March 2022, the Board approved exercising the 3rd and final option year to only extend the performance period fro...