SUBJECT: MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM UPDATE - LAS VIRGENES/MALIBU SUBREGION
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING:
1. Deobligating $41,834 in Measure M Multi-Year Subregional Program (MSP) - Active Transportation 1st/Last Mile Connections Program (Expenditure Line 56), as shown in Attachment A; and
2. Programming an additional $3,745,225 within the capacity of the Measure M MSP Highway Efficiency Program (Expenditure Line 57), as shown in Attachment B; and
B. AUTHORIZING the Chief Executive Officer (CEO) or their designee to negotiate and execute all necessary agreements and/or amendments for approved projects.
Issue
ISSUE
Measure M MSPs are included in the Measure M Expenditure Plan. All MSP funds are limited to capital projects. The annual update allows the Las Virgenes/Malibu Subregion and implementing agencies to approve new eligible projects for funding and revise the scope of work, schedule, and amend the project budget for previously funded projects. Funds are programmed through Fiscal Year (FY) 2029-30. The Board's approval is required to program additional funds and acknowledge the updated project lists (Attachments A & B), which serve as the basis for Metro entering into agreements and/or amendments with the respective implementing agencies.
Background
BACKGROUND
Based on the amount provided in the Measure M Expenditure Plan, a total amount of $166.89 million was forecasted to be available for programming for the subregion for FY 2017-18 to FY 2029-30 in Active Transportation/Transit/Tech Program (expenditure line 56) and Highway Efficiency Program (expenditure line 57). In prior actions, the Board approved programming $108.67 million in support of 30 projects. Therefore, $58.22 million is available to the Subregion for programming as part of this annual update. To date, $31.59 million (2...