OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
OCTOBER 15, 2026
Subject
SUBJECT: PICO RIVERA METROLINK STATION
Action
ACTION: RECEIVE ORAL REPORT
Heading
RECOMMENDATION
Title
RECEIVE oral report on the status of the Metrolink Pico Rivera station.
Issue
ISSUE
At its September 2026 meeting, staff provided a brief update on the Metrolink Pico Rivera station. In response, Director Hahn requested that staff return to the Committee with a further oral update on the project.
Background
BACKGROUND
During the development of the California High Speed Rail Authority’s (CHSRA) Draft Environmental Impact Report/Environmental Impact Statement (EIR/EIS) for the Los
Angeles – Anaheim Project Section, CHSRA identified the need to build a new rail viaduct in the City of Commerce that requires relocating the existing Commerce Metrolink Station as a formal mitigation. CHSRA proposes relocating the station 4,650 feet east of the current location to the City of Montebello. The identified area is surrounded by heavy industrial land uses; lacks transit and active transportation connectivity; is incompatible with adopted and emerging land use plans; and does not support short- or long-term ridership growth or transit-oriented community development, given the scale of investment. Current ridership at the station is 33 boardings per day.
In response to a February 2023 Metro Board motion (Attachment A), Metro initiated a feasibility study for a new commuter rail station within the City of Pico Rivera. The feasibility study was completed in December 2025 (Attachment B), and indicated a ridership estimate of 350-430 daily boardings. A cost-benefit analysis was not performed as part of the feasibility study but would be conducted should the project advance to the preliminary engineering (PE) phase.
Concurrent with the feasibility study, representatives from the cities of Commerce, Montebello, and Pico Rivera submitted a consensus letter to the Metro...