Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
NOVEMBER 20, 2025
Subject
SUBJECT: METRO E LINE UNDERGROUND TUNNEL RADIO SYSTEM REPLACEMENT
Action
ACTION: AWARD CONTRACT
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to award a firm-fixed price contract, Contract No. DR124275(2)000 to Martinez Engineering, LLC for the Metro E Line Underground Tunnel Radio System Replacement in the amount of $2,494,602, subject to the resolution of any properly submitted protest(s), if any.
Issue
ISSUE
The existing Metro E Line underground tunnel radio communications system equipment is nearing the end of its useful life and requires replacement. While still operational, the aging equipment provides critical radio communications for Metro Rail Operations, Rail Maintenance, the Metro Department of Public Safety (DPS), the Los Angeles County Sheriff's Department (LASD), the Los Angeles Fire Department (LAFD), and the Los Angeles Police Department (LAPD). The current system requires frequent maintenance to remain operational, and spare parts are challenging to find because they are no longer being manufactured.
Background
BACKGROUND
The Eastside Extension of the Metro E Line (formerly the Metro Gold Line Eastside Extension) opened for revenue service in 2009, running from Union Station to East Los Angeles. During construction, the radio communications system was installed to support critical radio operations in the underground tunnel segment. The Original Equipment Manufacturer (OEM) ceased business and discontinued the production of spare parts and technical support services for the radio system. Metro's Communication Systems Maintenance Department has been able to maintain the equipment and keep it operational. However, ongoing maintenance has become increasingly difficult due to the obsolescence of parts and equipment, making this approach unsustainable for long-term reliability.
Discussion
DISCUSSION
Under the contr...
Click here for full text