File #: 2018-0094   
Type: Project Status: Agenda Ready
File created: 3/5/2018 In control: Construction Committee
On agenda: 4/12/2018 Final action:
Title: APPROVE an increase in the Life of Project Budget (LOP) for Permeable Pavement and Bioretention Pilot Project (Project) in the amount of $1.16 million increasing the LOP from $940,000 to $2.1 million to complete construction of the Project.
Sponsors: Construction Committee
Indexes: Bids, Bioretention, Budget, Budgeting, Capital Project, Construction, Contractors, Division 04, Division 4 Concrete Pavement Pilot-Sustainability Implementation Program (Project), Grant Aid, Maintenance facilities, Procurement, Project, Safety, Water control
Attachments: 1. Attachment A - Procurement Summary C1160, 2. Attachment B - DEOD Summary
Related files: 2018-0253
Meeting_Body
REVISED
CONSTRUCTION COMMITTEE
APRIL 12, 2018

Subject
SUBJECT: PERMEABLE PAVEMENT AND BIORETENTION
PILOT PROJECT, DIVISION 4 MAINTENANCE
FACILITY

Action
ACTION: AUTHORIZATION FOR LIFE OF PROJECT BUDGET

Heading
RECOMMENDATION

Title
APPROVE an increase in the Life of Project Budget (LOP) for Permeable Pavement and Bioretention Pilot Project (Project) in the amount of $1.16 million increasing the LOP from $940,000 to $2.1 million to complete construction of the Project.

Issue
ISSUE

In 2014, Metro applied for a Proposition 84 Grant Opportunity to implement a permeable pavement project at Division 4. In May 2014, the State Water Resource's Control Board (SWRCB) awarded Metro with a grant of $752,000 to implement its proposed permeable pavement and biorentention project with a local commitment from Metro of $188,000 for a total LOP of $940,000. This report recommends adopting a LOP budget with the necessary additional funding of $1.16 million to complete the Project.
The competitive low-bid prices for the construction component of the Project have been received and the winning bid would result in this higher forecast for the LOP. Staff believes the bids are representative of current market conditions and that a rebid would not result in lower pricing. Furthermore, without additional funds, Metro will have to relinquish grant funding back to the SWRCB and terminate current efforts related to a much needed pilot.

Discussion
DISCUSSION

Project Description
The Permeable Pavement and Bioretention Pilot Project, Division 4 Maintenance Facility will replace approximately 40,000 square feet of hardscape with low-impact development (LID) stormwater infiltration features. Located in the City of Downey, Division 4 is directly adjacent to the Rio Hondo River. All stormwater from Division 4 currently drains directly into the Rio Hondo River. To address this runoff, Metro will install 39,140 square feet of permeable concrete pavement and 1,680...

Click here for full text