File #: 2017-0801   
Type: Contract Status: Agenda Ready
File created: 11/27/2017 In control: Ad Hoc Congestion, Highway and Roads Committee
On agenda: 1/17/2018 Final action:
Title: AUTHORIZE Contract Modification No. 221 (CCO 221) by the California Department of Transportation (Caltrans) for construction contract of Segment 3 of the I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) under Funding Agreement No. MOU.P0008355/8501A/A6, in the amount of $1,589,186.01 within the LOP budget.
Sponsors: Program Management (Department), Maria Luk
Indexes: Arroyo Verdugo subregion, Budget, Budgeting, Burbank, Construction, Contractors, Contracts, High occupancy vehicle lanes, I-5, I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 3 (Buena Vista To Magnolia) (Project), I-5 North County Capacity Enhancements, Interchanges, Project, Regional Surface Transportation Program, San Fernando Valley Service Sector, San Fernando Valley subregion, Southern California Highways, SR-118, SR-134, Subsidies
Related files: 2018-0015
Meeting_Body
AD HOC CONGESTION, HIGHWAY AND ROADS COMMITTEE
JANUARY 17, 2018


Subject
SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS FROM SR-134 TO
SR-118

Action
ACTION: AUTHORIZE CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE Contract Modification No. 221 (CCO 221) by the California Department of Transportation (Caltrans) for construction contract of Segment 3 of the I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) under Funding Agreement No. MOU.P0008355/8501A/A6, in the amount of $1,589,186.01 within the LOP budget.

Issue
ISSUE

CCO 221 authorizes compensation to the contractor in the amount of $1,589,186.01 for relocation of four City of Burbank - owned utilities at Front Street. Due to widening of the freeway at the Burbank Boulevard Interchange, the four utilities need to be relocated beyond the new State right of way line. The utilities run parallel to and across the freeway at and near Burbank Boulevard Bridge.

Discussion
DISCUSSION

The I-5 North Capacity Enhancement project includes freeway widening and construction of High-Occupancy Vehicle (HOV) lanes and other improvements between SR-134 and SR-118. Caltrans designed and is managing construction of the Project. Segment 3 of the I-5 North Capacity Enhancement Project is between Buena Vista Street and Magnolia Boulevard.

The freeway widening involves moving the westerly right-of-way line by approximately 50 feet to the west at the Burbank Boulevard Interchange, which requires the four utilities to be relocated outside of the new State right of way line. The work consists of relocation of a water line, a recycled water line, a sewer line, and an idle oil line south of the Burbank Boulevard Bridge near Cypress Avenue and Old Front Street. In the best interest of the Project and as per the request from the City of Burbank, these utility relocations will be accomplished as part of the overall freeway construction rather than through a separate City-le...

Click here for full text