SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS FROM SR-134 TO
SR-118
Action
ACTION: AUTHORIZE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
AUTHORIZE Contract Modification No. 221 (CCO 221) by the California Department of Transportation (Caltrans) for construction contract of Segment 3 of the I-5 North Capacity Enhancements Project between SR-134 and SR-118 (Project) under Funding Agreement No. MOU.P0008355/8501A/A6, in the amount of $1,589,186.01 within the LOP budget.
Issue
ISSUE
CCO 221 authorizes compensation to the contractor in the amount of $1,589,186.01 for relocation of four City of Burbank - owned utilities at Front Street. Due to widening of the freeway at the Burbank Boulevard Interchange, the four utilities need to be relocated beyond the new State right of way line. The utilities run parallel to and across the freeway at and near Burbank Boulevard Bridge.
Discussion
DISCUSSION
The I-5 North Capacity Enhancement project includes freeway widening and construction of High-Occupancy Vehicle (HOV) lanes and other improvements between SR-134 and SR-118. Caltrans designed and is managing construction of the Project. Segment 3 of the I-5 North Capacity Enhancement Project is between Buena Vista Street and Magnolia Boulevard.
The freeway widening involves moving the westerly right-of-way line by approximately 50 feet to the west at the Burbank Boulevard Interchange, which requires the four utilities to be relocated outside of the new State right of way line. The work consists of relocation of a water line, a recycled water line, a sewer line, and an idle oil line south of the Burbank Boulevard Bridge near Cypress Avenue and Old Front Street. In the best interest of the Project and as per the request from the City of Burbank, these utility relocations will be accomplished as part of the overall freeway construction rather than through a separate City-le...