Legislation Details

File #: 2026-0660   
Type: Project Status: Agenda Ready
File created: 8/31/2026 In control: Finance, Budget and Audit Committee
On agenda: 10/15/2026 Final action:
Title: CONSIDER: APPROVE an increase in Life-of-Project (LOP) budget for the Los Angeles Union Station West ADA Improvements Project #210191 (Project) by a total of $4,350,000, from $10,500,000 to $14,850,000; and AMEND the FY27 budget to increase funding for Project #210191 by $3,500,000 from $3,500,000 to $7,000,000.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - Union Station West ADA Scope and Phasing Map, 2. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
FINANCE, BUDGET, AND AUDIT COMMITTEE
OCTOBER 15, 2026

Subject
SUBJECT: LOS ANGELES UNION STATION (LAUS) WEST ADA IMPROVEMENTS PROJECT LIFE-OF-PROJECT BUDGET INCREASE

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
CONSIDER:

APPROVE an increase in Life-of-Project (LOP) budget for the Los Angeles Union Station West ADA Improvements Project #210191 (Project) by a total of $4,350,000, from $10,500,000 to $14,850,000; and

AMEND the FY27 budget to increase funding for Project #210191 by $3,500,000 from $3,500,000 to $7,000,000.

Issue
ISSUE

The Project currently has a Board-approved LOP budget of $10.5 million. The LOP was established in 2025 from a feasibility-level estimate based on conceptual design, five anticipated construction phases, preliminary assumptions regarding Metro environmental requirements, and no subcontractor pricing. As the design advanced to 95% construction documents, the Project incorporated additional stakeholder and operational requirements, expanded from 5 to 13 construction phases to maintain station operations and access during construction, incorporated full Metro environmental specifications, and experienced approximately 10% construction market escalation. The July 2026 pricing established a total Project cost of $14.85 million, resulting in a $4.35 million funding gap.

The Project implements Americans with Disabilities Act (ADA) corrective work required under an April 21, 2023, settlement agreement between the U.S. Department of Justice (DOJ) and Metro. The settlement agreement requires completion of applicable ADA corrective work by October 2026. Metro submitted a request for DOJ approval of a revised schedule allowing completion of the Project by May 2028. Approval of the LOP increase is necessary to maintain the proposed schedule and complete the Project by May 2028. Any revised deadline remains subject to DOJ approval.

Background
BACKGROUND

Early Planning and Programming
Followin...