Subject
SUBJECT: MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM UPDATE - ARROYO VERDUGO SUBREGION
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING:
1. programming of $9,874,631 within the capacity of Measure M Multi-Year Subregional Program (MSP) - Modal Connectivity and Complete Streets Projects and reprogramming of projects previously approved to meet the project schedules, as shown in Attachment A;
2. programming of $11,477,370 within the capacity of Measure M MSP - Transit Projects and reprogramming of projects previously approved to meet the project schedules, as shown in Attachment B;
3. inter-program borrowing and programming of $1,213,412 from the Subregion's Measure M MSP - Modal Connectivity and Complete Streets Projects to the Measure M MSP - Highway Efficiency, Noise Mitigation and Arterial Projects and reprogramming of projects previously approved to meet the project schedule, as shown in Attachment C;
4. programming of $3,465,970 within the capacity of Measure M MSP - Subregional Equity Program, as shown in Attachment D; and
B. AUTHORIZING the CEO or their designee to negotiate and execute all necessary agreements and/or amendments for approved projects.
Issue
ISSUE
Measure M MSPs are included in the Measure M Expenditure Plan, attached to the Measure M Ordinance. All MSP funds are limited to capital projects. The update allows the Arroyo Verdugo Subregion and implementing agencies to approve new eligible projects for funding and revise the project scope of work, budgets, and schedules for previously funded projects.
This update includes changes to projects that previously received Board approvals and funding allocations for new projects. Funds are programmed through Fiscal Year (FY) 2027-28. The Board's approval is required to update the project lists (Attachments A, B, C, and D), which serve as the basis for Metro to enter ...