File #: 2019-0655   
Type: Contract Status: Agenda Ready
File created: 8/16/2019 In control: Operations, Safety, and Customer Experience Committee
On agenda: 10/17/2019 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute Modification No. 2 to Contract No. PS14643013 with Mitsubishi Electric to provide elevator and escalator maintenance services for Gateway Building, increasing the seven (7) year base contract not-to-exceed amount by $850,000, from $4,467,975 to $5,317,975, effective December 1, 2019.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budgeting, Contract administration, Contracts, Elevators, Escalators, Gateway Building Costs (Project), Location 109, Los Angeles Union Station, Maintenance, Maintenance facilities, Procurement, Strategic planning
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - Contract Modification Change Order Log, 3. Attachment C - DEOD Summary
Related files: 2019-0800
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
OCTOBER 17, 2019


Subject
SUBJECT: GATEWAY BUILDING AND UNION STATION EAST COMPLEX ELEVATOR AND ESCALATOR SERVICES

Action
ACTION: APPROVE CONTRACT MODIFICATION

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Modification No. 2 to Contract No. PS14643013 with Mitsubishi Electric to provide elevator and escalator maintenance services for Gateway Building, increasing the seven (7) year base contract not-to-exceed amount by $850,000, from $4,467,975 to $5,317,975, effective December 1, 2019.

Issue
ISSUE

In September 2014, during this contract's period of performance, Metro assumed all maintenance responsibilities for the Union Station East Portal, including the seven (7) elevators and three (3) escalators for a total of 10 units. These units were added to this contract under Modification No. 1, however, funds added as part of the modification are insufficient considering the required and ongoing maintenance services.

To continue providing the critical and state mandated maintenance services for the 10 elevators and escalators at Union Station East Portal, Contract Modification No. 2 is required to increase the seven (7) year base contract amount by $850,000 from $4,467,975 to $5,317,975, effective December 1, 2019.

Background
BACKGROUND

On January 23, 2014, Metro Board of Directors awarded a seven (7) year base Contract No. PS14643013 to Mitsubishi Electric to provide state mandated elevator and escalator maintenance services for the Gateway Building.

In September 2014, Metro assumed all maintenance responsibilities for the Union Station East Portal, including the seven (7) elevators and three (3) escalators for a total of 10 units. These units were added to this contract under Modification No. 1, however, funds added as part of the modification are insufficient considering the required and ongoing maintenance services.

In 2015, this contract was t...