Title: APPROVE the following actions pertaining to the development and implementation of additional corridor mobility improvement projects (MIPs) on local arterials and local freeway interchanges experiencing congestion because of the discontinuity of the SR 710 North Freeway: A. APPROVE the attached Round 2 list of eligible MIPs recommended for funding (Attachments A and B); B. AUTHORIZE staff to program an additional $280 million in Measure R funds and $232.3 million in State and federal funds for a total of $512.3 million for the Round 2 MIPs starting in FY 2020-21; C. AUTHORIZE staff to reallocate $18 million in Measure R funds from three MIPs in the City of San Marino approved by the Board in December 2018 for projects to other projects due to the City's decision not to pursue those projects; D. AUTHORIZE staff to consolidate the $105 million Measure R funds allocated to the TSM/TDM Projects cleared under the SR-710 North Final Environmental Document with the Measure R funds fo...
Sponsors: Planning and Programming Committee
Indexes: Agreements, Budget, Budgeting, California Transportation Commission, Central Los Angeles subregion, City of Los Angeles, Congestion Mitigation And Air Quality Improvement Program, Corridor Improvements - Hwy (Project), Eric Garcetti, Guidelines, I-10, I-210, I-710, Interchanges, Intersections, Measure R, Motion / Motion Response, Pedestrians, Program, Project, Record Of Decision, Rehabilitation (Maintenance), Safety, San Fernando Valley subregion, San Gabriel, San Marino, South Bay Cities subregion, Southern California Highways, Strategic planning, Transportation Demand Management, Transportation system management, Travel demand management, Westside Cities subregion
Attachments: 1. Attachment A -SGV Rd 2 MIPs Recommended for Funding.pdf, 2. Attachment B - LA City LA County MIPs - Rd 2 Recommended for Funding, 3. Attachment C - Motion, 4. Attachment D - Rd 1 Project Sponsor Submittals, 5. Attachment E - Rd 1 MIPs Recommended for Funding, 6. Attachment F - Rd 2 Project Sponsor Submittals, 7. Attachment G - Rd 2 Recommended MIP Descriptions - SGV Cities Projects, 8. Attachment H - Rd 2 Recommended MIP Descriptions City County of LA, 9. Attachment I - Recommended Projects and Funding Allocations Summaries
Related files: 2019-0755
Meeting_Body
REVISED
PLANNING AND PROGRAMMING COMMITTEE
SEPTEMBER 18, 2019

Subject
SUBJECT: SR-710 NORTH CORRIDOR MOBILITY IMPROVEMENT PROJECTS - ROUND 2

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
APPROVE the following actions pertaining to the development and implementation of additional corridor mobility improvement projects (MIPs) on local arterials and local freeway interchanges experiencing congestion because of the discontinuity of the SR 710 North Freeway:

A. APPROVE the attached Round 2 list of eligible MIPs recommended for funding (Attachments A and B);

B. AUTHORIZE staff to program an additional $280 million in Measure R funds and $232.3 million in State and federal funds for a total of $512.3 million for the Round 2 MIPs starting in FY 2020-21;

C. AUTHORIZE staff to reallocate $18 million in Measure R funds from three MIPs in the City of San Marino approved by the Board in December 2018 for projects to other projects due to the City's decision not to pursue those projects;

D. AUTHORIZE staff to consolidate the $105 million Measure R funds allocated to the TSM/TDM Projects cleared under the SR-710 North Final Environmental Document with the Measure R funds for the MIPs under one "MIP" category for ease in managing and reporting all SR-710 North Corridor Mobility Improvements;

E. AUTHORIZE the CEO or his designee to negotiate and execute all necessary agreements with project sponsors to implement the approved MIPs; and

F. AUTHORIZE staff to approve changes in the number, scopes, and budgets of projects within the overall program approvals requested in this board report and consistent with the directives in Motion 29.1 (Attachment C).

Approval of the above recommendations will allow programming of all remaining Measure R, State and federal funds for the MIPs listed in this Board Report subject to the availability of funds.
Issue
ISSUE

At its December 2018 meeting, the Metro Board of Directors approved...