Legislation Details

File #: 2026-0617   
Type: Informational Report Status: Agenda Ready
File created: 8/11/2026 In control: 2028 Olympic & Paralympic Games/Quarterly Special Board Meeting
On agenda: 9/16/2026 Final action:
Title: RECEIVE AND FILE the Mobility Concept Plan (MCP) Implementation Progress Report.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
SPECIAL BOARD MEETING
SEPTEMBER 16, 2026

Subject
SUBJECT: 2028 MOBILITY CONCEPT PLAN IMPLEMENTATION REPORT

Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE the Mobility Concept Plan (MCP) Implementation Progress Report.

Issue
ISSUE

With a great deal of insight from the FIFA 2026 World Cup experience and less than two years before the opening ceremonies, Metro is entering a critical stage in the Games preparation process. For this special board meeting, staff will provide an update on key areas of progress and partnership, funding updates, and a six-month look ahead, including key milestones, for the priority workstreams driving Games preparation.

Background
BACKGROUND

Over the past four years, Metro has worked with LA28, Caltrans, Metrolink, the Los Angeles Department of Transportation (LADOT), the City of Los Angeles (COLA) Mayor’s Office, the Southern California Association of Governments (SCAG), and the Orange County Transportation Authority (OCTA), a group collectively known as the Games Mobility Executives (GME), as well as U.S. Secret Service, venue cities and Councils of Governments, to advance the 2028 Games Mobility Concept Plan approved by the Metro Board in December 2022. Following an extensive agency stakeholder outreach process, Metro and the GME identified a list of 15 priority workstreams. The GME then created subcommittees to advance the projects and programs under each workstream.

Discussion
DISCUSSION
Workstream Progress
Metro staff continues to work closely with regional partners to plan and deliver a safe, successful, and seamless 2028 Games for the region. Key achievements since the last update include:

Capital (Legacy) Projects
Released Request for Proposals (RFPs) for Games Multimodal Infrastructure Construction Manager/General Contractor (CM/GC) and A & E Lines Interlock Projects CM/GC.
Awarded Games Multimodal Infrastructure Project Construction Manager/General Contractor...

Click here for full text