Legislation Details

File #: 2026-0662   
Type: Project Status: Agenda Ready
File created: 9/1/2026 In control: Planning and Programming Committee
On agenda: 9/16/2026 Final action:
Title: CONSIDER: PROGRAMMING an amount not-to-exceed $35 million in Measure M I-710 South Corridor Project (now the LB-ELA CMIP) Highway Capital Funds as funding augmentation for the Shoreline Drive Realignment Project, subject to contingencies including partial repayment (Attachment A); AMENDING the FY 2027 Budget to accommodate this programming action; and AUTHORIZING the Chief Executive Officer or their designee to negotiate and execute all necessary agreements with the City of Long Beach.
Sponsors: Board of Directors - Regular Board Meeting
Attachments: 1. Attachment A - Contingencies for $35 Million of CMIP Funding, 2. Attachment B - City of Long Beach: Project Funding Details, 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
SEPTEMBER 16, 2026

Subject
SUBJECT: LONG BEACH-EAST LA CORRIDOR MOBILITY INVESTMENT PLAN HIGHWAY CAPITAL FUNDING

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
CONSIDER:

PROGRAMMING an amount not-to-exceed $35 million in Measure M I-710 South Corridor Project (now the LB-ELA CMIP) Highway Capital Funds as funding augmentation for the Shoreline Drive Realignment Project, subject to contingencies including partial repayment (Attachment A);

AMENDING the FY 2027 Budget to accommodate this programming action; and

AUTHORIZING the Chief Executive Officer or their designee to negotiate and execute all necessary agreements with the City of Long Beach.

Issue
ISSUE

The Board previously approved and programmed $9 million in funding for the Shoreline Drive Realignment Project (Project) to support the city of Long Beach’s efforts to complete the design phase in time to maintain a federal funding award and implement the Project in time for the 2028 Los Angeles Olympic and Paralympic Games (2028 Games). The Project currently faces a $35 million shortfall, which jeopardizes the federal funding award of $30 million and the Project's opening date. Staff recommend augmenting the prior funding allocation by an amount not-to-exceed $35 million to cover this shortfall, with contingencies included as outlined in Attachment A.

Background
BACKGROUND

The Project will realign Shoreline Drive to reduce speeds and traffic impacts, and create a larger, more functional, and more connected park space adjacent to the Los Angeles River at the point where Interstate 710 (I-710) connects to Downtown Long Beach via the Shoemaker Bridge. The Project also includes upgraded signal and intelligent transportation system infrastructure and approximately 1.5 miles of protected bicycle and pedestrian facilities that connect the city’s Downtown and waterfront, the Los Angeles River trail system, and neighborhoods wes...

Click here for full text