AUTHORIZE the Chief Executive Officer to execute Modification No. 3 to Contract No. OP749030003367 with Clean Energy to continue to provide Operation and Maintenance (O&M) services of Compressed Natural Gas (CNG) fueling stations at Divisions 1, 3, 5, 7, 10 and 18 and increase the Not-To-Exceed (NTE) amount of the first one-year option by $800,000 from $1,124,656 to $1,924,656, and exercise the first one-year option, increasing the total contract NTE amount from $9,462,159 to $11,386,815, and extend the period of performance from March 1, 2027 through February 29, 2028.
Issue
ISSUE
In November 2021, the Board approved the award of Contract No. OP749030003367 to Clean Energy for the operation and maintenance (O&M) of Metro’s compressed natural gas (CNG) fueling stations at Divisions 1, 3, 5, 7, 10, and 18. The base term expires on February 28, 2027, and staff must return to the Board to exercise the first of the five one-year options.
When the contract was established in 2021, the option-year funding was based on the anticipated transition from CNG buses to electric buses at these divisions. However, the transition timeline has since changed, and the affected divisions continue to rely on CNG fueling infrastructure. As a result, staff is requesting additional contract authority to ensure uninterrupted O&M services for these critical fueling facilities.
Background
BACKGROUND
Contract OP749030003369 with Clean Energy, which covers the operation and maintenance of the CNG compound at Division 1,3,5, 7,10, and 18 approved for a NTE amount of $5,285,439 for the five-year base period, and $5,623,284 for five, one-year option terms, for a combined NTE amount of $10,908,723. The scope...