File #: 2023-0111   
Type: Informational Report Status: Agenda Ready
File created: 2/14/2023 In control: Construction Committee
On agenda: 4/20/2023 Final action:
Title: RECEIVE AND FILE Office of the Inspector General Construction Change Order Spot Check Report for the period December 1 to February 28, 2022.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Budget, Budgeting, Carbon monoxide, Central Los Angeles subregion, City of Los Angeles, Construction, Contractors, Contracts, Crossovers, Disadvantaged business enterprises, Informational Report, Labor, Metro Equity Platform, Metro Rail A Line, Metro Rail D Line, Metro Rail E Line, Metro Rail L Line, Metro Vision 2028 Plan, Payment, Procurement, Program, Program Management, Project, Project management, Regional Connector Transit Corridor Project, Safety, San Fernando Valley subregion, South Bay Cities subregion, Statistics, Strategic planning, Transfers, Twenty-eight by '28 Initiative, Westside Cities subregion, Westside Subway Extension/Purple Line Extension Phase 1, Westside Subway Extension/Purple Line Extension Phase 2, Westside Subway Extension/Purple Line Extension Phase 3
Attachments: 1. Attachment A - Change Order Details for Spot Checks, 2. Attachment B - Tracking Sheet of OIG Recommendations and Responses, 3. Presentation
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
CONSTRUCTION COMMITTEE
April 20, 2023



Subject
SUBJECT: OFFICE OF THE INSPECTOR GENERAL
CONSTRUCTION CHANGE ORDER SPOT CHECKS

Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION
Title
RECEIVE AND FILE Office of the Inspector General Construction Change Order Spot Check Report for the period December 1 to February 28, 2022.

Issue
ISSUE
On January 25, 2018, the Metro Board directed the Office of the Inspector General ("OIG") to conduct random spot checks on change orders for the construction projects listed in the Quarterly Program Management report to ensure that the CEO Delegation of Authority to approve Construction Change Orders Policy is performing in the manner desired by the Board of Directors.

Background
BACKGROUND
The OIG's Construction Change Order Spot Check Program ("Spot Checks") focuses on approved change orders and modifications that exceed $500,000. The four change orders in this report were selected from the Program Management Quarterly Major Project Status, Legistar 2023-0176. The OIG gathers the data, reviews all the change orders over $500,000 and selects change orders from the major projects. The information for the Spot Checks was collected from the Program Management Information System (PMIS) which is the department's database system. Also, virtual meetings and telephonic interviews were conducted with Metro Program Management, Project Control, and Procurement staff from each involved project office.
For each Spot Check, we summarize:
* Description of the change order,
* Change order detail,
* Scope of Work,
* Budget,
* Schedule (Time to execute the change order),
* Safety, and
* Recommendations and Lessons Learned.
Metro's Program Control department has provided informal responses to this report before its issuance and are asked to provide written responses to the recommendations in this OIG Spot Checks Report within 30 days after this Report is issued. Included with this Report is a spreadsheet on the status of res...