SUBJECT: METRO CENTER PROJECT
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to:
A. AWARD a firm fixed-price contract, Contract No. C52151C1169-2 to S.J. Amoroso Construction Co. LLC, the responsive and responsible Proposer determined to provide Metro with the best value for the design and construction of the Metro Center Project (Project) in the amount of $81,487,000;
B. ALIGN the Life-of-Project Budget (LOP) of $112.7 million to $130,688,310 including $113.5 million state Prop 1B California Transit Security Grant (CTSG) fund, $7.3 million Federal Emergency Management Agency (FEMA) Transit Security Program grant funds and approximately $9.888 million of TDA Art 4 local funds;
C. AMEND the FY 21 LACMTA budget for the Project by $44,101,978 using Prop1B CTSG funds.
D. NEGOTIATE the Chief Executive Officer to negotiate and execute all agreements, task orders and contract modifications, including design-build options necessary up to the LOP budget to complete the above actions.
Issue
ISSUE
In March 2016, the Metro Board established the Life of Project budget (LOP) in the amount of $112.7 million based on the grant funds awarded to the Project. Since then - four years later, the preliminary engineering design, environmental work and selection of the design/build contractor have been completed. This Board action will award the design/build contract to S.J. Amoroso Construction Co. LLC deemed to provide the best value for the design and construction of the Project (See Attachment A, Procurement Summary) and align the LOP budget to $130,688,310 million to fund the design and construction of the Metro Center Project which comprises of the emergency operations center (EOC) and security operations center (SOC) including the option to accommodate a future 2nd floor for a new rail operations center (ROC) and/or bus operations cente...