Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
JUNE 18, 2015
Subject/Action
SUBJECT: GOLD LINE FOOTHILL EXTENSION
ACTION: AMEND FUNDING AGREEMENT TO INCREASE FUNDING FOR CEQA AND NEPA COMPLIANCE, ENGINEERING AND PRECONSTRUCTION ACTIVITIES FOR PHASE 2B
Heading
RECOMMENDATION
Title
APPROVED ON CONSENT CALENDAR amending the Metro Gold Line Extension Phase 2A Funding Agreement to increase funds for Phase 2B for environmental, engineering and preconstruction activities.
Issue
ISSUE
The October 2009 Long Range Transportation Plan (LRTP) identified $810.5 million associated with the Foothill Extension project (Pasadena to Claremont). Based on this amount, the Funding Agreement and subsequent amendments established an LOP budget for the Foothill Extension Phase 2A (Pasadena to Azusa) of $741 million. The balance of corridor funds remaining was $69.5 million for use on Phase 2A or Phase 2B (Azusa to Montclair) if authorized by the Board.
In January 2013 the Board amended the Funding Agreement to allow the Authority reimbursement of up to $36 million of the remaining $69.5 million for CEQA/NEPA compliance, preliminary engineering and planning for Phase 2B (Board Report Attachment A). Use of these funds was dependent on the Authority demonstrating that all work for Phase 2A could be constructed within the established LOP Budget of $741 million for Phase 2A. The Authority demonstrated that Phase 2A would be completed within the established LOP and was on schedule to achieve substantial completion in September 2015.
With the January 2013 Amendment, $33.5 million was left in unallocated corridor funds and available for Phase 2B upon Board approval.
Discussion
DISCUSSION
The Gold Line Foothill Extension is managed cooperatively between Metro and the Authority wherein the Authority is responsible for the design and construction of the project and Metro is responsible for funding, assuring the design and construction are complia...