Meeting_Body
REGULAR BOARD MEETING
MARCH 23, 2017
Subject/Action
SUBJECT: CRENSHAW/LAX TRANSIT CORRIDOR PROJECT
ACTION: ADOPT RESOLUTION OF NECESSITY TO ACQUIRE PARCELS HS-2701 AND HS-2701-1
Heading
RECOMMENDATION
Title
CONSIDER:
A. HOLDING a public hearing on the proposed Resolution of Necessity; and
B. ADOPTING the Resolution of Necessity authorizing the commencement of an eminent domain action to acquire Parcels HS-2701 (APN 4013-008-008) and HS-2701-1 (APN 4013-007-32, 022, 021 and 029), consisting of the real property and site improvements (hereinafter the "Property").
(REQUIRES TWO-THIRDS VOTE)
Issue
BACKGROUND
Acquisition of the Property (Attachment "A") located at 1119-1137 E. Redondo Blvd., and the parking lot on the south side of Redondo Blvd, west of West Blvd, City of Inglewood, is required for the construction and operation of a light rail transit alignment, roadway modifications, station, station amenities, parking and park & ride facilities, a traction power sub-station (TPSS), and related purposes for the Crenshaw/LAX Transit Corridor Project ("Project").
The Property to be acquired is an expansion of a previously adopted Resolution of Necessity (adopted on September 26, 2013) to acquire only Parcel HS-2701. At that time, Parcel HS-2701 was acquired to accommodate all of the station parking, station amenities and attendant portions of the Project, and was also to be used as a vital laydown yard for construction. Just prior to the adoption of the September 2013 Resolution of Necessity, Metro was made aware of a written parking lot covenant obligating 65 spaces within Parcel HS-2701 to one of the tenants of the Property. As the Project's schedule dictated a need for the possession of Parcel HS-2701 by a date certain, and the Project's design was complete, Metro moved forward with the condemnation of Parcel HS-2701, and filed an eminent domain action in Los Angeles Superior Court (LASC Case No. BC562344, "Eminent Domain Action")...
Click here for full text