File #: 2022-0188   
Type: Informational Report Status: Filed
File created: 3/23/2022 In control: Operations, Safety, and Customer Experience Committee
On agenda: 5/19/2022 Final action: 5/19/2022
Title: RECEIVE AND FILE the NextGen Bus Speed Engineering Working Group Status Update report in response to Motion 22.1.
Sponsors: Operations, Safety, and Customer Experience Commit
Indexes: Board approved a Motion, Budgeting, Bus Speed Improvements, City of Los Angeles, Eric Garcetti, Florence, Holly J. Mitchell, Informational Report, Metro Busway J Line, Metro Rail A Line, Motion / Motion Response, NextGen Bus Study, Outreach, Partnerships, Peak periods, Plan, Program, Ridership, Safety, South Bay Cities subregion, South Bay Service Sector, Surveys, Transit buses, Travel time
Attachments: 1. Presentation
Meeting_Body
OPERATIONS, SAFETY, AND CUSTOMER EXPERIENCE COMMITTEE
MAY 19, 2022

Subject
SUBJECT: MOTION 22.1: NEXTGEN BUS SPEED ENGINEERING WORKING GROUP STATUS UPDATE


Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE the NextGen Bus Speed Engineering Working Group Status Update report in response to Motion 22.1.

Issue
ISSUE

In July 2019, the Board approved Motion 22.1 entitled NextGen Bus Speed Engineering Working Group as part of the NextGen Service Concept. This motion requests the following:

A. Develop a list of priority bus supportive infrastructure projects needed to support the NextGen bus service plan, with an emphasis on near-term improvements that can be implemented concurrently with each phase of NextGen;
B. Form a NextGen Bus Speed Engineering Working Group co-chaired by the Metro CEO and the General Manager (GM) of the Los Angeles Department of Transportation (LADOT), or their designees, and establish a regular meeting schedule, at least monthly;
C. Assess the need for coordination with additional local jurisdictions and municipal operators where bus delay hotspots exist; and
D. Report back to the Operations, Safety and Customer Experience Committee on the above in April 2020, and quarterly thereafter.

This update provides details regarding a technical working group appointed by Metro and its efforts to coordinate with a complementary group from the Los Angeles Department of Transportation (LADOT) to develop a work program to improve bus priority and assess the need to coordinate with other jurisdictions and municipal operators.

Since July 2019, 10 lane miles of bus priority lanes have been installed, representing an increase of 53% in bus lane miles within City of Los Angeles and up to 30% in improved travel speeds on specified bus routes has been achieved. This report provides a status update as of FY22 Q3 ending March 31, 2022.

Background
BACKGROUND

In July 2018, the Board adopted Motion 38....