Subject
SUBJECT: SEPULVEDA TRANSIT CORRIDOR PROJECT
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
A. AUTHORIZE the Chief Executive Officer (CEO) to award the following two (2) Contracts, subject to resolution of protests, if any.
a. Contract No. PS66773MRT to LA SkyRail Express, a special purpose corporation to be formed between John Laing Investments Limited and BYD Transit Solutions LLC, for pre-development services for a proposed Monorail technology transit solution concept ("TSC") in an amount not to exceed $63,605,132.
b. Contract No. PS66773HRT to Sepulveda Transit Corridor Partners -Bechtel, a special purpose vehicle to be formed between Bechtel Development Company, Inc., Meridiam Sepulveda, LLC and American Triple I Partners, LLC, for pre-development services for a proposed Heavy Rail technology transit solution concept ("TSC") in an amount not to exceed $69,882,427.
B. APPROVE Contract Modification Authority in the amount of 25% for each of the two contract award values, respectively, and authorize the CEO to execute individual Contract Modifications within the Board-approved Contract Modification Authority.
Issue
ISSUE
On October 31, 2019, Metro issued Request for Proposals (RFP) No. PS66773 seeking up to two qualified contractors to perform pre-development work for the Sepulveda Transit Corridor Project on a firm fixed price basis, with the potential opportunity for one of the contractors to enter into an Implementation Agreement for project delivery after completion of the pre-development work. Metro will determine which developer (if any) will have the opportunity to potentially proceed with implementation.
The Statement of Work, as included in the RFP, is broken out into five phases. Metro may choose not to issue a Notice to Proceed for any phase, in its sole discretion. In addition, if a Contractor's Transit Solution Concept (TSC), as refined...