Subject
SUBJECT: LONE HILL TO WHITE DOUBLE TRACK FINAL DESIGN, PLANS SPECIFICATIONS & ESTIMATES
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATIONS
Title
AUTHORIZE the Chief Executive Officer (CEO) to:
A. REPROGRAM $769,688 in project savings from Lone Hill to White (LHW) Preliminary Engineering to LHW Final Design and establish Life of Project Final Design budget of $8,269,688 inclusive of all third-party and design-related costs;
B. AWARD and EXECUTE a firm fixed price Contract No. AE73891000 with Moffatt and Nichol, for engineering services for the LHW Final Design Plans, Specifications and Estimates (PS&E) project, in an amount of $6,498,899 subject to resolution of protest(s), if any; and
C. ENTER INTO and EXECUTE all contracts, task orders and agreements within the Life of Project budget including third party agreements necessary to complete the LHW Final Design project.
Issue
ISSUE
In December 2019, the Metro Board programmed funds for Lone Hill to White (LHW) Final Design (see Attachment A). Staff is returning to the Board to seek approval of the life of project budget for the LHW final design and award the engineering services final design plans, specifications and estimates to Moffat and Nichol. Additionally, the staff recommended actions includes reprogramming project savings from the LHW Preliminary Engineering phase to the Final Design phase.
Discussion
BACKGROUND
The LHW double track project consists of adding 4 miles of a second main line track along the Metro-owned San Gabriel subdivision located in the cities of San Dimas and La Verne that serves Metrolink San Bernardino Line (see Attachment B). Approximately 70% of the San Bernardino Line is single track. Single track limits capacity and makes it challenging for trains to recover from operational delays. LHW will ultimately add four miles of double track to provide more capacity and make it ea...