Meeting_Body
CONSTRUCTION COMMITTEE
JANUARY 20, 2022
Subject
SUBJECT: STATE ROUTE 71 (SR-71) IMPROVEMENTS (SOUTH SEGMENT): UPGRADE 1.8 MILES OF THE EXISTING EXPRESSWAY TO A 6-LANE FWY BETWEEN MISSION BLVD AND LOS ANGELES/SAN BERNARDINO COUNTY LINE
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
AUTHORIZE Contract Modification No. 17 (CCO 17) for payment to the California Department of Transportation (Caltrans) for the construction contract of South Segment of the SR-71 Improvements Project between Mission Blvd and Los Angeles/San Bernardino County Line (The Project) in an amount not to exceed $4.5 million within the overall corridor Life of Project (LOP) budget.
Issue
ISSUE
The construction contract for SR-71 improvements between Mission Blvd and Los Angeles/San Bernardino County Line encountered several problems including special requirements for excavation near the SCE power poles, utilities conflicts not identified during design, contaminated soil, and third-party delays. When the contractor started excavating for the construction of drainage culverts in August 2021, contaminated soil was encountered. Further investigations confirmed the presence of arsenic. The excavation work was immediately halted. Caltrans determined that the contaminated soil had to be appropriately disposed under the EPA regulations.
After consulting with disposal sites that are permitted to accept arsenic-contaminated soil, Caltrans estimated an approximated cost of $4.5 million to properly dispose the excavated soil.
Contract modifications exceeding $500,000 require Board authorization. ...