Meeting_Body
CONSTRUCTION COMMITTEE
JUNE 16, 2016
Subject/Action
SUBJECT: CRENSHAW/LAX TRANSIT PROJECT
ACTION: AUTHORIZE THE CHIEF EXECUTIVE OFFICER (CEO) TO EXECUTE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
CONSIDER:
A. AUTHORIZING the CEO to execute a Contract Modification to Contract No. C0988 with Walsh/Shea Corridor Constructors (WSCC), to design and construct a bus transfer facility for $2,200,000, increasing the total contract price from $1,294,476,149.38 to $1,296,676,149.38 for the Crenshaw/LAX Transit Project;
B. APPROVING an increase in Contract Modification Authority (CMA) for Contract No. C0988, in the amount of $2,200,000, increasing the total CMA from $134,699,993 to $136,899,993;
C. ADOPTING a Life-of-Project (LOP) Budget of $2,200,000 for the Bus Transfer Facility; and
D. AUTHORIZING the execution of this Contract Modification subject to final execution of the 3% Local Match funding agreement between Metro and the City of Inglewood.
Issue
ISSUE
A notice-to-proceed was issued to Walsh/Shea Corridor Constructors (WSCC) on September 10, 2013 for Contract No. C0988. The C0988 contract included three park- and-ride facilities: Expo/Crenshaw Station, Fairview Heights Station, and Downtown Inglewood Station. The Metro Board approved a bus transit facility at the Downtown Inglewood light rail station during the November 2015 Board meeting. This was also approved by the South Bay Cities Council of Governments (COG) in November 2015. Changing the park-and-ride facility at the Downtown Inglewood station into a bus transit facility is a change to the Contract No. C0988 and requires a Contract Modification.
Discussion
DISCUSSION
The Metro Board approved a bus transit facility at the Downtown Inglewood light rail facility at the November 2015 Board meeting. The South Bay Cities COG also approved the project in November 2015. The Final Environmental Impact Statement /Final Environmental Impact Report (FEIS/FEIR), which was adop...
Click here for full text