File #: 2015-0501   
Type: Program Status: Passed
File created: 5/7/2015 In control: Planning and Programming Committee
On agenda: 6/17/2015 Final action: 6/25/2015
Title: APPROVED ON CONSENT CALENDAR: A. preliminary transportation modal category funding marks; and B. fund estimate of $199.4 million; and. C. release of preliminary recommendations for the 2015 Countywide Call for Projects (Call) for distribution.
Sponsors: Planning and Development (Department)
Indexes: Bicycling, Board approved a Motion, Budgeting, California Transportation Commission, Call For Projects, Congestion Mitigation And Air Quality Improvement Program, Debt, Funding plan, Long Range Transportation Plan, Metrolink, Pedestrians, Program, Proposition C, Regional Transportation Improvement Program, Regional Transportation Planning Agency, Repayment of Capital Project Loan Funds, Short Range Transportation Plan, Southern California Association Of Governments, State Transportation Improvement Program, Subsidies, Technical Advisory Committee, Transportation Improvement Program, Transportation modes, Vehicle miles of travel
Attachments: 1. 2015 CFP Funding Marks - final attachment a, 2. 15Call Prelim Recom Attachment B 5-26-15, 3. 2015 CFP Funding Marks - attachment c, 4. Presentation_Handout 0501

Meeting_Body

REVISED

PLANNING AND PROGRAMMING COMMITTEE

JUNE 17, 2015

 

Subject/Action

SUBJECT:                      2015 CALL FOR PROJECTS

 

ACTION:                      APPROVE PRELIMINARY FUNDING MARKS, AND FUND ESTIMATE

                                          AND PRELIMINARY RECOMMENDATIONS FOR DISTRIBUTION

 

Heading

RECOMMENDATION

 

Title

APPROVED ON CONSENT CALENDAR:

 

A.                     preliminary transportation modal category funding marks; and

B.                     fund estimate of $199.4 million; and.

C.                     release of preliminary recommendations for the 2015 Countywide Call for Projects (Call) for distribution.

 

Issue
ISSUE

 

The Board initiated the 2015 Call for Projects to allocate transportation funds now available for regionally significant projects that public agencies may implement.  Staff has identified preliminary transportation modal category funding marks and a preliminary fund estimate to assist in the development of preliminary recommendations.  The preliminary review of the 2015 Call applications has been completedThese preliminary recommendations are presented in the Rainbow Report, distributed separately to the Board, and will be released to project sponsors, subject toupon Board approval of the funding marks and fund estimate.  Staff will initiate the Technical Advisory Committee (TAC) review and appeals process leading to the September Board approval.

 

Discussion
DISCUSSION

 

The preliminary modal category funding marks (Attachment A) are based on the regional program direction provided in the adopted 2009 Long Range Transportation Plan (LRTP).  The fund estimate of $199.4 million (Attachment B) is based on the 2015 funding availability and priorities as adopted by the Board.  Evaluation criteria used to select the projects include a “Complete Streets” integrated, multimodal transportation network, consistency with Senate Bill (SB) 375 goals of reducing Vehicle Miles Traveled (VMT) and Greenhouse Gas Emissions (GHGe), and First/Last Mile access to the transit system.  The preliminary fund estimate is based on federal, state, and local funds forecasts used in the adopted 2009 LRTP (as updated in March 2015).

 

Background

 

Federal statute (Title 23 U.S.C. 134 (g) & (h)) and state statute (P.U.C. 130303) require Metro to prepare a Transportation Improvement Program (TIP) for Los Angeles County.  The TIP allocates revenues across all surface transportation modes based on the planning requirements of the federal Moving Ahead for Progress in the 21st Century Act (MAP-21).

 

Metro accomplishes these mandates, in part, by programming transportation revenues through the Call for Projects process wherein Los Angeles County jurisdictions and transit agencies may apply for funding for regionally significant projects.  These regionally significant projects are often beyond the fiscal capabilities of local sponsors.  The Call for Projects process provides an opportunity for these projects to be funded to meet the County’s transportation needs.  The Call for Projects implements Metro’s multi-modal programming responsibilities for Los Angeles County and the Board-adopted 2009 LRTP.

 

Funding Marks

 

The preliminary fund estimate is based on the Board-adopted 2009 LRTP assumptions, as updated in March 2015, and includes federal, state, and local funds.  Forecasts for the local fund sources in Attachment B are consistent with the LRTP update and Metro’s Debt policy.  Federal funding forecasts are based on historical trends, but are adjusted to reflect federal Highway Trust Fund growth rates and possible downside risks (e.g., possible reductions in the amount of Congestion Mitigation and Air Quality Improvement [CMAQ] Program funds).  State fund forecasts are based on historical trends, but do not reflect growth, assuming higher priority needs such as state highway safety, maintenance, and operating costs.  The State Regional Improvement Program (RIP) funding is subject to the actual 2016 State Transportation Improvement Program (STIP) fund estimate to be adopted by the California Transportation Commission in August 2015.  The specific funding sources chosen for the 2015 Call for Projects are subject to change based upon the projects finally selected and other factors, including eligibility and availability.

 

The modal category funding marks are provided as preliminary minimums (percentage for each mode) and are based on the relative modal shares from the Board-adopted 2009 LRTP, combined with the Board-approved motion on September 16, 2010 with regard to increasing the bicycle modal funding percentage from seven to 15 percent as well as the Board-approved motion on April 25, 2013 increasing the pedestrian modal funding percentage from seven to 10 percent.  The Board will need to determine the final funding levels for each category based on the regional significance and demonstrated evaluation criteria benefit of the specific projects that the eligible sponsors submitted in the 2015 Call for Projects process.

 

Per the September 2009 motion, the Board directed that a five- to 10-percent reserve be established to allow the TAC through the appeals process to consider potential meritorious projects that might be recommended for funding.  Staff initially created a 10-percent TAC Appeals reserve fund; however, to comply with additional Board direction, staff has shifted a portion of the TAC reserve to increase the bicycle and pedestrian improvements modal funding marks leaving a $5.9 million (3%) reserve balance.

 

Preliminary Recommendations

 

Preliminary recommendations for the 2015 Call are provided in the “Rainbow Report” which was distributed separately to the Board.  In order to maintain scoring consistency across all modes, projects assigned a score of 70 points or higher are eligible for funding, as directed by the September 24, 2009 Board-approved motion.  Those projects are indicated in the Rainbow Report by a solid, “qualifying” line.

 

Staff modal evaluation has found that the Regional Surface Transportation Improvements (RSTI), Bicycle Improvements, Pedestrian Improvements, and Transit Capital modes have more “qualified” projects than could be funded within their funding marks.  The sum total of the seven projects recommended for funding beyond the modal marks is approximately $4.47 million for these four modes, about two percent of the funding available in this Call.

 

Attachment C shows a surplus of $4,213,492 in the Goods Movement Improvements mode, $125,809 in the Signal Synchronization and Bus Speed Improvements mode, and $739,672 in the Transportation Demand Management mode.  Staff proposes to fund the seven projects, mentioned above, with $4,470,846, using a portion of the funds from these three modes to supplement the preliminary funding marks shown in Attachment A. 

 

Staff proposes to reallocate the remaining $608,127 to the 2015 Call for Projects TAC Appeals Reserve, thereby increasing the TAC Appeals Reserve to $6,590,127.

 

Subject to Upon Board approval of the preliminary funding marks and fund estimate, these preliminary recommendations will be released to the public in early July in the Rainbow Report and reported to TAC, who will hold the funding recommendations appeals process in July.  Based on funding appeals, TAC will also have the opportunity to recommend additional projects to receive funding (successful appeals), using the TAC Reserve Fund.

 

Determination_Of_Safety_Impact
DETERMINATION OF SAFETY IMPACT

 

The 2015 Call will not have any adverse safety impacts on our employees and patrons.

 

Financial_Impact
FINANCIAL IMPACT

 

The 2015 Call does not have an impact on the FY15 budget.  Funding of $199.4 million for the 2015 Countywide Call for Projects will be included in FYs 2016-17, 2017-18, 2018-19, 2019-20, and 2020-21 budgets in cost centers 0441 - Subsidies to Others and 0442 - Subsidies to Others.  Since this is a multi-year program, the cost center manager, Chief Planning Officer, and Executive Director of Engineering and Construction will be accountable for budgeting the costs in future years.

 

Consistent with the Metro Board’s approval of the Short Range Transportation Plan (SRTP) in July 2014, funding for the Plan, including the Call for Projects, assumes borrowing consistent with Metro’s debt policies.  The funding marks here may consist of bond funds backed by Proposition C.  After these bonds are issued, the debt service is assigned to the appropriate sub-fund within Proposition C.  The funding mark for Proposition C 25% funds is $89.3 million spread over five years as shown in Attachment B.  In year six, assuming level debt service and a 30-year term at the SRTP-assumed interest rate of 4.5%, we find that if all of the $89.3 million is attributed to such a borrowing, the annual debt service including principal and interest will be $5.9 million of Proposition C 25% funds in FY 2021 and beyond.  The funding mark for Proposition C 10% is $10.2 million also spread over five years as shown in Attachment B.  In year six, using the same borrowing assumptions, the annual debt service including principal and interest will be $667,000 of Proposition C 10% in FY 2021 and beyond.  The Proposition C 10% bond funding approach, if necessary, will impact future possible subsidies to Metrolink by up to $667,000 per year.  These assumptions are all consistent with the SRTP.

 

Impact to Budget

 

The sources of funds for these activities are: Proposition C 10%, Proposition C 25%, Repayment of Capital Projects Loan Funds, Congestion Mitigation and Air Quality (CMAQ), and Regional Improvement Program (RIP) [State Transportation Improvement Program (State TIP)].  The Proposition C 10% and Proposition C 25% funds fund balances are exhausted and approval of this action will require debt issuance.  These funds are not eligible for Metro bus and rail operating and capital expenditures.  RIP funds cannot be used for transit operating expenses.

 

While CMAQ funds are eligible for operating purposes or transit capital, there are no additional operating expenses eligible under CMAQ funding.  CMAQ funds could be used for transit capital purposes.  Los Angeles County must strive to fully obligate its share of CMAQ funding by May 1st of each year, otherwise Metro risks its redirection to other California Regional Transportation Planning Agencies by Caltrans.  Staff recommends the use of long-lead-time CMAQ funds as planned to ensure utilizing our federal funds.

 

In light of new state and federal funding programs such as the Active Transportation Program managed through the Southern California Association of Governments (SCAG) and the California Transportation Commission (CTC) and the state Cap and Trade Program, staff recommends that the Call process seek to maximize opportunities to leverage Call funding with other programs.

 

Alternatives_Considered
ALTERNATIVES CONSIDERED

 

The Board could adjust the preliminary fund estimate or the modal category funding marks, or defer the 2015 Call for Projects modal marks entirely.  Adjusting the funding marks is not recommended because they are consistent with the adopted 2009 LRTP and subsequent Board direction.  Staff understands Metrolink needs but the SRTP financial forecast adopted by the Board in March 2015 balances the needs of the Call with those of Metrolink.  Deferring the 2015 Call for Projects modal marks decision also is not recommended because funds are expected to be available and some allocation process is necessary, so that Metro may fulfill its statutory transportation programming responsibilities.  For example, Metro would not be positioned to submit the statutorily required 2016 Regional Transportation Improvement Program (TIP) for Los Angeles County to SCAG and the California Transportation Commission (CTC) by the required December 2015 deadline. Los Angeles County’s State TIP funding priorities will be set for the six-year period ending in FY 2020-21 and the Call for Projects is our established process for that purpose.

 

Next_Steps
NEXT STEPS

 

Upon Board approval, staff will release the preliminary funding recommendations (“Rainbow Report”) to the public.  The Rainbow ReportThe recommendations will be posted online on June 29th and mailed on July 6th.  Applicants will be given an opportunity to appeal their project scores to TAC on July 28th and 29th where TAC will be able to make recommendations for the distribution of the TAC Reserve Fund.  The Board is scheduled to formally adopt the 2015 Countywide Call for Projects at its September meeting.

 

Attachments

ATTACHMENTS

 

Attachment A - 2015 Countywide Call for Projects Preliminary Modal Category Funding Marks

Attachment B - 2015 Countywide Call for Projects Preliminary Fund Estimate

Attachment C - 2015 Countywide Call for Projects Recommended Changes to Preliminary Modal Category Funding Marks

 

Prepared_by

Prepared by: Brad McAllester, Executive Officer, (213) 922-2814

                                          Wil Ridder, Executive Officer, (213) 922-2887

                                          Renee Berlin, Managing Executive Officer, (213) 922-3035

 

 

Reviewed_By

Reviewed By: Martha Welborne, Chief Planning Officer, (213) 922-7267

                                           Nalini Ahuja, Executive Director, Finance & Budget, (213) 922-3088