File #: 2015-1316   
Type: Contract Status: Passed
File created: 8/19/2015 In control: System Safety, Security and Operations Committee
On agenda: 1/21/2016 Final action: 1/28/2016
Title: AWARD a not-to-exceed Contract under Bid No. IFB MA17204 to Worthington Cylinder, the lowest responsive and responsible bidder, for the procurement for Indefinite Delivery, Indefinite Quantity for Compressed Natural Gas (CNG) fuel (cylinder) tanks for an amount not-to-exceed $1,462,181.00 inclusive of sales tax.
Indexes: Bids, Budgeting, Bus Acquisitions, Contracts, Fuels, Operations Maintenance (Project), Procurement, Purchasing
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - DEOD Summary

Meeting_Body

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE

JANUARY 21, 2016

 

Subject/Action

SUBJECT:                     COMPRESSED NATURAL GAS FUEL CYLINDERS

 

ACTION:                     APPROVE CONTRACT AWARD

 

Heading

RECOMMENDATION

 

Title

AWARD a not-to-exceed Contract under Bid No. IFB MA17204 to Worthington Cylinder, the lowest responsive and responsible bidder, for the procurement for Indefinite Delivery, Indefinite Quantity for Compressed Natural Gas (CNG) fuel (cylinder) tanks for an amount not-to-exceed $1,462,181.00 inclusive of sales tax.

 

Issue

ISSUE

 

In 1998, Metro initiated an Accelerated Bus Replacement program for its transit bus fleet. Between 1999 and 2002, over 1,200 40’ CNG buses were purchased. All of these buses used CNG cylinders that cannot be used after they reach their 15 year expiration limits.  CNG cylinders are tested and date stamped for a given lifespan. Federal regulations do not permit the use of CNG cylinders past their expiration dates, and there is no known process to recertify or otherwise extend the life of CNG cylinders.

 

Discussion

DISCUSSION

 

Metro has been purchasing an average of 200 buses annually and continues to receive new buses under the current contract with New Flyer. However due to the Accelerated Bus Replacement program in 1999, there remains a short-term equipment deficit for the next few years. Purchasing cylinders for a replacement program is necessary to bridge this time gap and minimize the impact on bus service.  

 

The first series of buses targeted for CNG fuel cylinder replacement are 2000-01 New Flyer 5300 Series buses with repowered engines.  The New Flyer buses have expiring CNG cylinders and have been removed from service.  The CNG cylinders being purchased are designed to fit in this particular type of bus.  Current inventory and this contract will enable Bus Maintenance to replace CNG fuel cylinders in 150 buses.  It is anticipated that additional buses will be required for CNG fuel cylinder replacement depending on future bus service requirements at which point supplemental procurements will be initiated.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

Award of contract will result in a positive impact on safety. Replacing the CNG cylinders on the bus will help ensure the safe and compliant operation of the vehicle.

 

Financial_Impact

FINANCIAL IMPACT

 

The funding of $1,462,181.00 for these fuel cylinders is included in the FY16 budget in cost center 3366, under project 306002, Operations Maintenance and line item 50441, Parts- Revenue Vehicle.

 

Impact to Budget

 

The source of funds for this procurement will come from Federal, State and local funding sources that are eligible for Bus and Rail Operating or Capital Projects.  These funding sources will maximize the use of funds for these activities.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The alternative is not to award this master agreement contract and procure CNG cylinders on an as-needed basis, using the traditional "min/max" replenishment system method. The "min/max" replenishment system method calculates minimum and maximum inventory levels. This strategy is not recommended since it does not provide for a commitment from the supplier to ensure availability, timely delivery, continued supply and guaranteed fixed price CNG cylinders.

 

Unless additional funding is identified to procure new buses, there are no alternative options available other than replacing CNG cylinders on Metro buses with expiring cylinders. Not pursuing this strategy will impact the quantity of buses available for revenue service and would necessitate service reductions.

 

Next_Steps

NEXT STEPS

 

Upon receipt of the new CNG cylinders, 5300 series buses will be brought to the Central Maintenance Shops for removal of expired fuel cylinders and installation of new cylinders.  

 

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - DEOD Summary

 

Prepared_by

Prepared by:                      Amy Romero, Director, (213) 922-5709

Christopher Reyes, Transportation Planning Manager III, Operations (213) 922-4808

Reviewed_By

Reviewed by:                      Ivan Page, Interim Executive Director, Vendor/Contract Management

James T. Gallagher, Chief Operations Officer