File #: 2015-1329   
Type: Contract Status: Consent Calendar
File created: 8/21/2015 In control: Board of Directors - Regular Board Meeting
On agenda: 1/28/2016 Final action: 1/28/2016
Title: AUTHORIZE Contract Modification No. 32 (a.k.a. Contract Change Order, CCO 32) by Caltrans for Segment 3 construction contract of the I-5 North Capacity Enhancements project from SR-134 to SR-118 under the Funding Agreement No. MOU.P0008355/8501 A/A6, in the amount of $2,100,000 without an increase in the project budget or contract value.
Sponsors: Program Management (Department), Maria Luk
Indexes: Arroyo Verdugo subregion, Budgeting, Burbank, Construction, Contractors, Contracts, Dynamic Signage, High occupancy vehicle lanes, I-5, I-5 N Hov Lanes Sr-134 To Sr-118 - Segment 3 (Buena Vista To Magnolia) (Project), I-5 North County Capacity Enhancements, Interchanges, Measure R, Project, San Fernando Valley Service Sector, San Fernando Valley subregion, Southern California Highways, SR-118, SR-134, SR-170

Meeting_Body

CONSTRUCTION COMMITTEE

JANUARY 21, 2016

 

Subject/Action

SUBJECT:                     I-5 NORTH CAPACITY ENHANCEMENTS FROM SR-134 TO SR-118 (FUNDING AGREEMENT NO. MOU.P0008355/8501 A/A6)

 

ACTION:                     AUTHORIZE CONTRACT MODIFICATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE Contract Modification No. 32 (a.k.a. Contract Change Order, CCO 32) by Caltrans for Segment 3 construction contract of the I-5 North Capacity Enhancements project from SR-134 to SR-118 under the Funding Agreement No. MOU.P0008355/8501 A/A6, in the amount of $2,100,000 without an increase in the project budget or contract value.

 

 

Issue

ISSUE

 

Metro provides partial funding for the I-5 North Capacity Enhancements project from SR-134 to SR-118 through an MOU with the State of California Department of Transportation (Caltrans). Caltrans is currently managing construction of the project. A $2,100,000 change order for relocation of water mains within the project limits is necessary to accommodate construction of the new Empire Avenue interchange.

 

Contract modifications exceeding $500,000 require Board authorization per the Staff Delegations of Contract Action Approval and Award Authority memorandum dated February 23, 2010.

 

Discussion

DISCUSSION

 

The I-5 North Capacity Enhancements project is divided into five segments:

Segment 1A  :

Widen I-5 for an HOV lane from SR-118 to SR-170.  Reconstruct I-5/SR-170 mixed flow connector. Construct soundwalls.

Segment 1B  :

Install Changeable Message Sign (CMS) on I-5 Northbound at Los Feliz Blvd.

Segment 2  :

Widen I-5 for an HOV lane from SR-170 to Buena Vista Street

Segment 3  :

Widen I-5 for an HOV lane from Buena Vista Street to Magnolia Boulevard. Reconstruct Burbank Boulevard and Empire Avenue interchanges

Segment 4  :

Widen I-5 for an HOV lane from Magnolia Boulevard to SR-134

 

This Board report involves only Segment 3 of I-5 North Projects. The total programmed budget for Segment 3 remains $402,381,000. Construction, including the plant establishment period, is expected to be completed in September 2019. The contract is about 32% complete.

CCO 32 is to reimburse Caltrans for the cost of utility potholing and, removing and relocating three existing City of Burbank water pipes in Empire Avenue and Victory Place in conjunction with the construction of the new Empire Avenue Interchange.

Two of the three pipes will be replaced with new pipes in the new alignment of Empire Avenue. The third will be installed in the new Victory Place Bridge. The City of Burbank is preparing the engineering plans for the referenced relocations. These three water pipes are identified to be removed and relocated during the construction by others in the contract document. This CCO will be performed by Caltrans’ contractor in order to minimize the delays and the interferences with the construction of Empire Avenue interchange and Victory Place Bridge.

This CCO work was budgeted under right of way capital originally and is now performed by Caltrans’ contractor under the construction capital. Metro will be working with Caltrans to shift the budgeted right of way capital funds for this work to the construction capital funds, to replenish the contingencies. 

The budgeted contingency for the project is $39,833,356. Authorization of CCO 32 in the amount of $2,100,000 will allow Caltrans to complete the work at Empire Avenue and Victory Place Separation and prevent project delays. The cost of this CCO does not increase the overall budget, it will be funded from the current project budget. The remaining contingency after CCO 32 will be $5,944,760.

 

Considerations

 

Project Budget Assessment

The cost of referenced CCO is within the project budget. Metro Highway Program has been working with Caltrans to continuously assess the various risks, and has requested that Caltrans evaluate and maintain the financial status of each segment in the corridor. Based on the current risk assessment and financial analysis, this segment is anticipated to be completed within the current project budget.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

There is no impact to safety by approving this action.

 

Financial_Impact

FINANCIAL IMPACT

 

Metro’s contribution of $7,800,000 Measure R 20% Highway Fund for FY16 for the I-5 North Capacity Enhancements project - Segment 3 is included in Account 54001 - Subsidies to Others, in cost center 0442, under project number 460334 - I-5 North Capacity Improvements, Segment 3. Local funding is only a portion of the total project programmed funds. The changes identified herein are within the project budget. Since this is a multi-year contract/project, the Managing Executive Officer of Highway Program or designee will be accountable for budgeting the cost in future years for LACMTA’s share within the existing project budget.

 

Impact to Budget

 

The source of funds for the payment of this CCO is Measure R 20% Highway Funds, which is not eligible for bus or rail operations.

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to approve this change order. However, such disapproval would result in an immediate impact in schedule with an estimated 8 to 12 months delay and potential higher cost from $3,100,000 to $5,000,000 due to a minimum of $7100 per day for the delay cost plus potential claim by the Contractor.

Next_Steps

NEXT STEPS

 

Upon approval of this CCO by the Board, staff will work with Caltrans to expedite the changes to allow the project to move forward.

 

Prepared_by

Prepared by:

Victor Gau, Senior Engineering Manager, Highway Program (213) 922-3031

Aline Antaramian, Deputy Executive Officer, Highway Program (213) 922-7589

Aziz Elattar, Executive Officer, Highway Program (213) 922-4715

 

 

Reviewed_By

Reviewed by:                      

Richard Clarke, Executive Director, Program Management (213) 922-7557