File #: 2015-1759   
Type: Contract Status: Consent Calendar
File created: 12/10/2015 In control: Board of Directors - Regular Board Meeting
On agenda: 1/28/2016 Final action: 1/28/2016
Title: CONSIDER: A. INCREASING the Life of Project budget for Project 809081, Red Line Segment 2 Close-out in the amount of $336,697, increasing the previous authorization amount of $31,510,403 to $31,847,100; B. AMENDING the FY 16 budget to add $187,500 to Project 809081, Red Line Segment 2 Close-out; C. INCREASING the Life of Project budget for Project 809082, Red Line Segment 3 Close-out in the amount of $556,900, increasing the previous authorization amount of $3,639,000 to $4,195,900; and D. AMENDING the FY16 budget to add $62,500 to Project 809082, Red Line Segment 3 Close-out.
Sponsors: Construction Committee
Indexes: B Line (Red) Segment 3, Budget, Budgeting, Construction, Contracts, Metro Red Line, Project, Proposition A, Red Line MOS-2 North, Red Line MOS-2 West, Red Line Seg 2 Closeout (Project), Red Line Seg3 North Hollywood Closeout (Project)

Meeting_Body

CONSTRUCTION COMMITTEE

JANUARY 21, 2016

 

Subject/Action

SUBJECT:                     RED LINE SEGMENT 2 CLOSE-OUT AND RED LINE SEGMENT 3

                                          CLOSE-OUT

 

ACTION:                     AUTHORIZATION FOR INCREASE THE LIFE OF PROJECT BUDGETS

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     INCREASING the Life of Project budget for Project 809081, Red Line Segment 2 Close-out in the amount of $336,697, increasing the previous authorization amount of $31,510,403 to $31,847,100;

 

B.                     AMENDING the FY 16 budget to add $187,500 to Project 809081, Red Line Segment 2 Close-out;

 

C.                     INCREASING  the Life of Project budget for Project 809082, Red Line Segment 3 Close-out in the amount of $556,900, increasing the previous authorization amount of $3,639,000 to $4,195,900; and

 

D.                     AMENDING the FY16 budget to add $62,500 to Project 809082, Red Line Segment 3 Close-out.

 

 

Issue

ISSUE

 

Litigation arising out of the construction of Red Line Segment 2 and Segment 3 is on-going.  The remaining litigation is now in the appellate stage.  The current LOPs for Segment 2 and Segment 3 do not include amounts necessary for the appellate services now required, and thus are not sufficient to fund the remaining litigation necessary to close out these projects.

 

The Life of Project Budgets for Project 809081, Red Line Segment 2 Close-Out and Project 809082, Red Line Segment 3 Close-Out need to be increased to fund the above described costs.

 

Financial Impact

FINANCIAL IMPACT

 

This action will increase the FY16 budget as follows: 

 

1.                     Adding $187,500 to Cost Center 1210, under Project 809081, Red Line Segment 2 Close-out, account 50302 - legal services; and

 

2.                     Adding $62,500 to Cost Center 1210, under Project 809082, Red Line Segment 3 Close-out, account 50302 - legal services;

 

These increases will be funded with Proposition A 35%.

 

This action will increase the Life of Project budget for Project 809081 from $31,510,403 to $31,847,100 and the Life of Project budget for Project 809082 from $3,639,000 to $4,195,900.  Since this is a multi-year project, the Executive Director Program Management will be responsible for monitoring the Life of Project budget and General Counsel will be responsible for budgeting the expense in future years.


IMPACT ON BUS AND RAIL OPERATING AND CAPITAL BUDGET

 

The funding for this action will come from Proposition A 35%.  No other sources of funds were considered because this fund is the appropriate fund for rail close-out project.

 

The funding for this Life of Project increase is available for rail operating and capital projects.

 

This activity will not impact ongoing operating costs. 

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board can choose not to increase the Life of Project budget for Project 809081, Red Line Segment 2 Close-out and/or Project 809082, Red Line Segment 3 Close-out.  This is not recommended as Metro must have funds to pay ongoing litigation costs. 

 

Prepared_by

Prepared by:                      

 

Bryan Pennington, Deputy Executive Director, Program Management (213) 922-7449

Charles Safer, Assistant County Counsel, (213) 922-2511

 