Subject/Action
SUBJECT: MEASURE R HIGHWAY SUBREGIONAL PROGRAM (MRHSP)
ACTION: APPROVE ADOPTION OF UPDATED PROJECT LIST
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING the updated project list and changes in the funding levels for the Measure R Highway Subregional Program (MRHSP) in Arroyo Verdugo, Las Virgenes Malibu, South Bay, North County, and Gateway Cities Subregions as shown in Attachment A.
B. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute all necessary agreements for approved projects.
C. APPROVING time extension for 1 project as shown in Attachment B
Issue
ISSUE
The project lists for the MRHSP are updated to provide each subregion with the opportunity to revise the proposed Measure R Highway Program implementation plan. The updated attached project lists include projects which have already received prior Board approval, as well as proposed changes related to schedule, scope, funding allocation and the addition or removal of projects. The Board's approval is required as the updated project lists are the basis for Metro to enter into agreements with each respective implementing agency,
Discussion
DISCUSSION
The Measure R Expenditure Plan included the following projects in the Highway Subregional Program
* Highway Operational Improvements in Arroyo Verdugo subregion
* Highway Operational Improvements in Las Virgenes/Malibu subregion
* I-405,I-110,I-105, and SR-91 Ramp and Interchange Improvements in South Bay
* State Route 138 Capacity Enhancements in North County
* I-605 Corridor "Hot Spots" Interchanges in Gateway Cities
* I-710 South and/or Early Action Projects in Gateway Cities
These projects are not fully defined in the Measure R Expenditure Plan. Definition, development, and implementation of specific projects are done through collaborative efforts by Metro's Highway Program staff, the respective COGs and the project sponsor.
At the Dec...