File #: 2016-0726   
Type: Contract Status: Agenda Ready
File created: 8/31/2016 In control: System Safety, Security and Operations Committee
On agenda: 11/17/2016 Final action:
Title: AUTHORIZE the Chief Executive Officer to increase the total authorized not-to-exceed amount to Rail Operations Engineering Support Bench (Bench) Contract No OP39202965, by $4,300,000 from $5,000,000 to $9,300,000 for engineering and technical services for wayside systems operating and capital projects.
Indexes: Budgeting, Capital Project, Capital Project Funds, Contracts, Maintenance, Maintenance of way, Procurement, Professional Services, Systems engineering
Attachments: 1. Attachment A - Procurment Summary, 2. Attachment B – List of Proposed Project Uses, 3. Attachment C - Change Log GEC Bench, 4. Attachment D - DEOD Summary
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE

NOVEMBER 17, 2016

 

Subject/Action

SUBJECT:                     RAIL OPERATIONS ENGINEERING SUPPORT BENCH

 

ACTION:                     INCREASE CONTRACT VALUE

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to increase the total authorized not-to-exceed amount to Rail Operations Engineering Support Bench (Bench) Contract No OP39202965, by $4,300,000 from $5,000,000 to $9,300,000 for engineering and technical services for wayside systems operating and capital projects.

 

Issue

ISSUE

 

Metro Rail Maintenance and Engineering has limited number of resources to develop and execute capital projects and, at the same time, meet the day-to-day engineering support needs that are necessary to maintain and improve Metro wayside assets and systems. The current Bench requires an increase in contract authority to allow the continued provision of engineering and technical services as-needed in situations where Metro does not have sufficient capacity or expertise necessary to perform a task.

 

Discussion

DISCUSSION

 

In April 2013, the Board authorized the award of Contract No. OP39202965, in the amount of $5,000,000, to 25 qualified firms, for a range of support services for wayside systems and equipment that included train control, traction power, communications, and fare collection. The services also included civil design as well as computer-aided design and drafting (CADD) services. This Bench has enabled Metro to supplement internal resources by having available a wide range of firms with specialized engineering knowledge. A list of proposed project uses is shown in Attachment B. This action will provide additional contract authority, which is needed to provide an increased amount of engineering and technical services through the end of the current Period of Performance, March 30, 2018.

 

To date, the value of bench task orders and modifications that has been awarded is $2,334,206; the additional value of pending task orders is $2,488,300, for a total Bench amount of $4,822,506.  A list of all task awards by firm and project description is shown in Attachment C.                     

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

This Bench contract is not directly related to a specific safety issue. However, the services provided via the Bench will contribute to maintaining the rail system in a State of Good Repair (SGR) which is essential to providing a safe and reliable service for riders who use the Metro rail system daily. 

 

Financial_Impact

FINANCIAL IMPACT

 

For FY 17, funding of $5,201,157 is included in the operating budget and $5,567,632 is included in the capital project budget under various cost centers and projects, including cost centers: 6821- Asset Management,  3910 - Maintenance and Engineering, 3922 - Rail Communications Systems, 3926 - Rail Signal Systems, 3927 - Rail MOW Track Maintenance, 3928 - Rail Traction Power Systems, 3960 - Rail Transit Engineering, and 3962 - SCADA Systems Engineering & Maintenance, Account 50316 -Professional and Technical Services.

 

These funds will be used for contract task orders to support operating and capital project needs. Since this is a multi-year contract, the cost center manager(s) and project manager(s) will ensure funding needs are budgeted in future years.

 

Impact to Budget

 

The source of funds for operating related task orders is Enterprise operating funds. For capital related task orders, the source of funds will be dependent on the specific capital project funding. No other sources of funds were considered for this activity because it supports Maintenance of Way (MOW) engineering operating and capital projects.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

1) Solicit competitive bids for each individual task as it becomes due. This is not recommended as it would require extensive additional staff time to process each request and result in project delays due to the lead time required to complete each procurement cycle. Additionally, procuring these services on a per-assignment basis would impose significant additional burden on the Procurement Department.

 

2) Engage a single, large engineering firm as a "one stop shop". This approach has been used in the past but staff has experienced challenges with getting assistance with smaller projects. The wide range of firms on this bench ensures that Wayside Systems can receive the necessary specialized engineering knowledge, and gives small, disadvantaged firms an opportunity to provide services.

 

3) Utilize existing Engineering staff to provide the required technical support. This is not feasible as the current budgeted MOW Engineering capacity is fully utilized to maintain Metro's existing systems and oversee the development of the new rail lines. Also, there would not be sufficient existing staff to re-assign to provide technical support to the various capital projects concurrently.

 

Next_Steps

NEXT STEPS

 

Upon Board approval, staff will continue to competitively award individual task orders as needed for engineering and technical support services for wayside systems operating and capital projects.

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - List of Proposed Project Uses

Attachment C - Task Order Log  

Attachment D - DEOD Summary

 

Prepared_by

Prepared by:                      Frank Alejandro, Senior Executive Officer, Rail Maintenance and Engineering (Interim)

Geyner Paz, Senior Administrative Analyst (213) 617-6251

 

Reviewed_By

Reviewed by:                      James T. Gallagher, Chief Operations Officer (213)922-4424


Debra Avila, Chief Vendor/Contract Management Officer (213) 418-3051