File #: 2016-0803   
Type: Contract Status: Agenda Ready
File created: 10/3/2016 In control: System Safety, Security and Operations Committee
On agenda: 11/17/2016 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 3 to Contract No. OP33673132, with Xlnt Tint of Anaheim, Inc., for glass panel surfaces anti-graffiti film maintenance and replacement services, to exercise the first and second year options in the amount of $1,304,442 for each of the first and second year options, for a combined total of $2,608,884, increasing the total contract value from $4,342,589 to $6,951,473 and extending the contract term from February 3, 2017 to February 2, 2019.
Indexes: Budgeting, Contractors, Contracts, Graffiti, Maintenance, Procurement, Vandalism
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B – Contract Modification-Change Order Log, 3. Attachment C - DEOD Summary.
Meeting_Body
REVISED
SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE
NOVEMBER 17, 2016

Subject/Action
SUBJECT: ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT SERVICES AND ETCHED GLASS REPAIR SERVICES

ACTION: EXERCISE FIRST AND SECOND YEAR OPTIONS

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 3 to Contract No. OP33673132, with Xlnt Tint of Anaheim, Inc., for glass panel surfaces anti-graffiti film maintenance and replacement services, to exercise the first and second year options in the amount of $1,304,442 for each of the first and second year options, for a combined total of $2,608,884, increasing the total contract value from $4,342,589 to $6,951,473 and extending the contract term from February 3, 2017 to February 2, 2019.

Issue
ISSUE

There are approximately 102,788 square feet of glass panel surfaces throughout the Metro transit system. Under the existing contract, on-going anti-graffiti film maintenance and replacement services are performed on a regular basis to protect the glass surfaces and mitigate vandalism system-wide.

The three-year base period for this Contract will expire on February 2, 2017. The contractor has been providing satisfactory maintenance services. A Contract Modification is required to exercise each of the two, one-year options extending the period of performance through February 2, 2019.

Discussion
DISCUSSION

Under this Contract, the contractor is required to perform once a month inspections of the protected glass panel surfaces throughout Metro facilities with a 100% replacement of the etched and damaged anti-graffiti film. On an average, 800,000 square feet of glass anti-graffiti film is replaced annually due to repeated etching damage and other types of vandalism.

The service frequencies will remain the same for each of the two, one-year options. This service is necessary to ensure clean and well maintained Metro stations and facilities free of graff...