File #: 2017-0070   
Type: Contract Status: Passed
File created: 2/1/2017 In control: Construction Committee
On agenda: 2/16/2017 Final action: 2/23/2017
Title: CONSIDER: A. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute Modification(s) to Contract No. C0991 with Hensel Phelps/Herzog JV, for the column bent construction for the potential Los Angeles World Airports (LAWA) Automated People Mover accommodations in an amount not-to-exceed $3,220,000 increasing the total contract value from $170,573,106 to $173,793,106; B. APPROVING an increase in Contract Modification Authority (CMA) for Contract No. C0991 in the amount of $3,220,000 increasing the total CMA from $17,231,269 to $20,451,269; and C. AUTHORIZING the CEO to enter into a funding agreement with Los Angeles World Airports.
Indexes: Airport Metro Connector (AMC) Station Project, Budgeting, Construction, Contracts, Crenshaw/LAX Transit Corridor Project, Division 16, LAX/Metro Transit Center Station, Los Angeles International Airport, Maintenance, Maintenance facilities, Metro Crenshaw Line, Metro Exposition Line, Metro Green Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, National Environmental Policy Act Of 1969, Plan, Procurement, Terminal 27, Westchester
Attachments: 1. Attachment A - Procurement Summary SWY.pdf, 2. Attachment B -Contract Modification - Change Log SWY.pdf, 3. Attachment C - DEOD Summary.pdf, 4. Attachment D-Potential LAWA APM Plan View, 5. Attachment E-Potential LAWA APM Cross Section
Meeting_Body

CONSTRUCTION COMMITTEE
FEBRUARY 16, 2017



Subject/Action
SUBJECT: DIVISION 16: SOUTHWESTERN YARD PROJECT

ACTION: APPROVE CONTRACT MODIFICATIONS FOR ACCOMMODATING POTENTIAL LOS ANGELES WORLD AIRPORTS AUTOMATED PEOPLE MOVER

Heading
RECOMMENDATION

Title
CONSIDER:

A. AUTHORIZING the Chief Executive Officer (CEO) to negotiate and execute Modification(s) to Contract No. C0991 with Hensel Phelps/Herzog JV, for the column bent construction for the potential Los Angeles World Airports (LAWA) Automated People Mover accommodations in an amount not-to-exceed $3,220,000 increasing the total contract value from $170,573,106 to $173,793,106;

B. APPROVING an increase in Contract Modification Authority (CMA) for Contract No. C0991 in the amount of $3,220,000 increasing the total CMA from $17,231,269 to $20,451,269; and

C. AUTHORIZING the CEO to enter into a funding agreement with Los Angeles World Airports.

Issue
ISSUE

A Notice-to-Proceed was issued to Hensel Phelps/Herzog JV on June 29, 2015 for the design and construction of the Division 16 Southwestern Yard maintenance facility. The design-builder has substantially completed final design for the Division 16 maintenance facility, has commenced construction of the maintenance building, and is in the process of constructing the track facility as part of the C0991 Contract. Los Angeles World Airports (LAWA) has requested Metro to construct an accommodation for the potential Automated People Mover (APM) foundations at one location between the Metro maintenance yard lead track and the main line tracks (see Attachments D and E).

Discussion
DISCUSSION

Metro and LAWA have been coordinating the planning of the Airport Metro Connector (AMC) 96th Street Transit Station Project to provide regional transit connectivity to the Los Angeles International Airport (LAX) and the LAWA Landside Access Modernization Program (LAMP) program. Subject to the outcome of LAWA's environmental clearance processes, va...