File #: 2017-0173   
Type: Contract Status: Passed
File created: 3/9/2017 In control: Construction Committee
On agenda: 5/18/2017 Final action: 5/25/2017
Title: FINDING that use of the design-build project delivery approach for Metro Emergency Security Operations Center Project pursuant to Public Contract Code ??22160-22169 to reduce project costs, expedite project completion and allow for negotiation and award of a design-build contract to a responsible proposer whose proposal is determined to be the best-value to Metro. (REQUIRES 2/3 VOTE OF THE BOARD)
Sponsors: Planning and Programming Committee
Indexes: Bids, Board approved Life-of-Project Budget, Budgeting, Construction, Contract administration, Contractors, Contracts, Design build, Emergency Operations Center, Emergency Security Operations Center (Project), Metro Center Street Project, Procurement, Professional Services, Project, Project delivery, Project management, Safety, Security, Tenants
Meeting_Body
CONSTRUCTION COMMITTEE
MAY 18, 2017

Subject/Action
SUBJECT: METRO EMERGENCY SECURITY OPERATIONS CENTER PROJECT

ACTION: APPROVE USE OF DESIGN-BUILD CONTRACT DELIVERY APPROACH

Heading
RECOMMENDATION

Title
FINDING that use of the design-build project delivery approach for Metro Emergency Security Operations Center Project pursuant to Public Contract Code ??22160-22169 to reduce project costs, expedite project completion and allow for negotiation and award of a design-build contract to a responsible proposer whose proposal is determined to be the best-value to Metro.

(REQUIRES 2/3 VOTE OF THE BOARD)

Issue
ISSUE

Metro is authorized to enter into design-build contracts pursuant to Public Contract Code ??22160-22169. The recommended action will provide staff with the authority to use a competitively negotiated procurement method for the selection of a recommended contract award.

Discussion
DISCUSSION

In March 2016, the Board approved the life of project (LOP) budget in the amount of $112.7 million for the Emergency Security Operations Center (ESOC) Phase One, CP No. 212121; and award of a 36-month firm fixed priced Contract No. AE451150019779 to HDR Engineering, Inc., in the amount of $5,936,638 for architectural and engineering design services for the ESOC. The proposed ESOC will consist of approximately 80,000 square feet and four story hardened structure with at-grade parking. The ESOC will be at a minimum a Leadership in Energy and Environmental Design (LEED) Silver certified and built in phases with the first phase consisting of the core and shell for the four story structure with at-grade parking including the tenant improvements for the Emergency Operations Center (EOC), Security Operations Center (SOC) and law enforcement dispatch to be located on the 2nd and 4th floors. Phase Two will consist of the tenant improvements for the Rail Operations Center (ROC) and Bus Operations Center (BOC) on the remaining 2nd and 3rd floor...