File #: 2017-0513   
Type: Project Status: Agenda Ready
File created: 7/19/2017 In control: System Safety, Security and Operations Committee
On agenda: 10/19/2017 Final action: 10/26/2017
Title: CONSIDER: A. APPROVING Life-Of-Project budget for the capital project, Transit Facilities Hardening, in the amount of $1,280,800; and B. AMENDING the FY18 Budget in the amount of $885,800
Sponsors: System Safety, Security and Operations Committee
Indexes: Access control (Transportation), Budget, Budgeting, Capital Project, Grant Aid, Labor, Law enforcement, Metro Divisions, Project, Safety and security, Security, Surveys, Threats, Transportation Security Grant Program
Attachments: 1. Attachment A - Project summary schedule, 2. Attachment B - Financial Forecast

 

Meeting_Body

 

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE

OCTOBER 19, 2017

 

 

Subject

SUBJECT:                     TRANSIT FACILITIES HARDENING

 

Action

ACTION:                     AUTHORIZATION FOR LIFE OF PROJECT BUDGET

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     APPROVING Life-Of-Project budget for the capital project, Transit Facilities Hardening, in the amount of $1,280,800; and

 

B.                     AMENDING the FY18 Budget in the amount of $885,800

 

Issue

ISSUE

 

For Metro’s safety and security services to be effective, the continuous assessment of threats against our personnel and assets must be conducted. As the assessments are conducted, the upgrade of existing physical security equipment and procedures must occur due to the changing threat, equipment life cycle and the increased operational requirements. 

 

Staff has anticipated the changing environment by requesting funding from DHS through the Transit Security Grant Program (TSGP) for improving the physical security equipment at five Divisions. Staff is requesting approval of the Life-Of-Project for the capital project with the grant from DHS, the Mass Transit Passenger Screening and Facilities Hardening for $1,280,800.  This approval will authorize staff to proceed with providing additional cameras, fencing and security kiosks at five critical Metro facilities that are in need of an upgrade, or “hardening.”

 

Discussion

DISCUSSION

 

In FY16, staff submitted an Investment Justification Application under FY16 DHS Transit Security Grant Program (TSGP) to secure funding for physical security equipment hardening. DHS awarded Metro $1,130,800 to complete the project, and the period of performance is September 1, 2016 to August 31, 2019.  The fund allocation was developed through conducting physical security surveys at the listed divisions, and the staff determined that the divisions that were assessed are in the greatest need for improvement in their physical security posture.  The surveys included determining the number of CCTV cameras that were in each location, and the view of each camera, the number of security kiosks for the contract guard force, the number and location of access control devices on doors, and the condition of the perimeter walls and lighting at the facilities.  The hardening of Metro facilities will encompass the following:

 

                     The divisions that were assessed by the Metro staff are mission essential areas which significant deficiencies were found in the current physical security posture to warrant improvement.

                     These locations will have additional high definition CCTV cameras installed at yard locations where visibility is lacking. The increased number of cameras will improve the situational awareness of the personnel monitoring the cameras.

                      Security kiosks will be installed at entrance and exit locations with viewing of property with CCTV cameras to detect any intrusion. These locations are very large, and the increased presence will be effective in deterring threats to our personnel and equipment.

                     Enhance and add access control devices to secure employee access and egress points. Additional access control devices will protect our employees and equipment from unauthorized entry.

                     Build walls with perimeter lighting to prevent theft and vandalism. Several locations need improved perimeter walls and lighting to present a hard target effect of our facilities and to deter unauthorized access.

 

Staff is anticipating the completion of the construction and implementation of the additional devices in August 2019.

 

Determination_of_safety_impact

DETERMINATION OF SAFETY IMPACT

 

This capital project expenditure will provide a positive safety impact to Metro employees, contractors and the public by providing enhanced safety and security against threats as well as provide better situational awareness and promote better behaviors from all.

 

Financial_impact

FINANCIAL IMPACT

 

Staff is requesting to amend the FY18 budget in the amount of $785,800, and $100,000 in labor for this capital project, in cost center 2610, System Security and law Enforcement. Since this is a multi-year project, the executive officer of System Security and Law Enforcement is responsible for budgeting in future years. 

 

Impact to Budget

 

The DHS Grant funds of $1,130,800 of this project, are eligible for bus and rail operating and capital improvements, although the grant award is for this specific project. The $150,000 for Direct Labor ATU will be funded with TDA Article 4 funds, which are eligible for bus and rail operating and capital improvements.

 

Alternatives_considered

ALTERNATIVES CONSIDERED

 

An option considered would be not to approve the funding from the Department of Homeland Security Grant Program. This alternative is not recommended because the   hardening of Metro facilities is a necessary step to continue to improve our physical security posture at our facilities through threat evaluation and the life cycle of deployed equipment.

 

Next_steps

NEXT STEPS

 

Upon approval of recommendation, staff will set up the LOP and the FY18 annual budget for the capital project and commence work.

 

 

Attachments

ATTACHMENTS

 

Attachment A - Project Summary Schedule

Attachment B - Financial Forecast

 

Prepared_by

Prepared by:  Susan Walker, Director of Physical Security, System Security and Law Enforcement, (213) 922-7464

 

Reviewed_By

Reviewed by:  Alex Wiggins, Chief Systems Security and Law Enforcement Officer, (213) 922-4433