File #: 2017-0618   
Type: Contract Status: Passed
File created: 9/12/2017 In control: Construction Committee
On agenda: 10/19/2017 Final action: 10/26/2017
Title: CONSIDER: A. FINDING that awarding a design-build contract pursuant to Public Utilities Code Section 130242 (a) will achieve certain private sector efficiencies in the integration of design, project work, and components related to electrification for the Division 20 Portal Widening Turnback Project; and (REQUIRES TWO-THIRDS VOTE OF THE BOARD) B. AUTHORIZING the Chief Executive Officer to solicit and award a low bid design-build contract for the electrification improvements required for the Division 20 Portal Widening Turnback Project, pursuant to Public Utilities Code Section 130242.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Bids, Budgeting, Construction, Contract administration, Contracts, Design build, Div. 20 Portal Widening Turnback (Project), Division 20, Division 20 Portal Widening Turnback Facility Project, Electrification, Metro Purple Line, Metro Rail B Line, Metro Rail D Line, Metro Red Line, Procurement, Project, Testing, Westside Subway Extension/Purple Line Extension Phase 1

Meeting_Body

CONSTRUCTION COMMITTEE

OCTOBER 19, 2017

 

Subject

SUBJECT:                     DIVISION 20 PORTAL WIDENING TURNBACK PROJECT

 

Action

ACTION:                     APPROVE USE OF DESIGN-BUILD CONTRACTING DELIVERY APPROACH

 

Heading

RECOMMENDATION

 

Title

CONSIDER:

 

A.                     FINDING that awarding a design-build contract pursuant to Public Utilities Code Section 130242 (a) will achieve certain private sector efficiencies in the integration of design, project work, and components related to electrification for the Division 20 Portal Widening Turnback Project; and

 

(REQUIRES TWO-THIRDS VOTE OF THE BOARD)

 

B.                     AUTHORIZING the Chief Executive Officer to solicit and award a low bid design-build contract for the electrification improvements required for the Division 20 Portal Widening Turnback Project, pursuant to Public Utilities Code Section 130242.

 

Issue

ISSUE

Metro is authorized to enter into design-build contracts pursuant to Public Utilities Code Section 130242. This section requires that the Board make the finding set forth in Recommendation  A. This action is in conformance with Metro's typical business process and procedures for award of low-bid design-build contracts.

 

Discussion

DISCUSSION

 

The primary benefit of the design-build process is a shortened project schedule where the design-builder is able to start construction while the design is being completed.  For the Division 20 Portal Widening Turnback project, a separate design-build contract to complete design, manufacture, furnish, and test the new traction power supply substation and emergency backup power generator in the Red/Purple Line Yard is critical before the main portal widening and turnback facility construction can commence.  The proposed location of the turnback facility directly impacts the existing power substation and emergency backup power generator.  The turnback facility cannot be built until the new power substation is constructed and tested and the existing one is removed.

 

Implementing a design-build delivery method for the electrification of the Div 20 Portal Widening Turnback Project ensures Metro will meet the revenue service date for Purple Line Section 1 per the Federal Funding Granting Agreement.    Other possible benefits of a design-build process include additional efficiencies in project management, administration, and coordination.

 

Award for this design-build contract will be made on a low-bid basis.

 

Financial_Impact

FINANCIAL IMPACT

 

This project is funded on a fiscal year basis under project number 865519 - Division 20 Portal Widening Turnback Project.  No additional funding is required for the proposed recommendation. Funding for the procurement activities are included in the approved budget of $76.9M through FY18.  Staff will develop a Life of Project (LOP) budget recommendation as designs are finalized and a contract award amount is eminent for the primary workscope. The Project Manager, Cost Center Manager and Chief of Program Management is responsible for budgeting in future fiscal years.

 

Impact to Budget

 

The FY18 budget is funded with Measure R 35% and State Transit and Inter City Rail Capital Program (TIRCP) sources.  These funding sources are designated for this project and does not have an impact to Operations eligible funding.  No other funds were considered.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

This work could be accomplished under the main construction contract when that solicitation goes out for bid.   Staff does not recommend this approach because doing so would extend the construction duration of the portal widening and turnback facility by at least another 12-14 months, thereby jeopardizing the FFGA for Purple Line Extension Section 1. 

 

Next_Steps

NEXT STEPS

Staff will prepare a design-build solicitation package. Procurement will commence in early 2018 upon approval of this item.

 

 

 

Prepared_by

Prepared by: Rick Meade, Senior Executive Officer, Program Management (213) 922-7917

                                          

 

Reviewed_By

Reviewed by: Richard Clarke, Chief Program Management Officer (213) 922-7557