File #: 2017-0634   
Type: Agreement Status: Agenda Ready
File created: 9/19/2017 In control: Construction Committee
On agenda: 11/16/2017 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute the Utility Cooperative Agreement (UCA) between Metro (Authority) and XO Communications.
Sponsors: Construction Committee
Indexes: Construction, Construction Support, Project, Utility Cooperative Agreement
Attachments: 1. Attachment A - Utility Cooperative Agreement XO COMM FINAL 10-25-16_FR-r2
Related files: 2017-0808

Meeting_Body

CONSTRUCTION COMMITTEE

NOVEMBER 16, 2017

 

Subject

SUBJECT:                     XO COMMUNICATION UTILITY COOPERATIVE

AGREEMENT

 

Action

ACTION:                     XO COMMUNICATION UTILITY COOPERATIVE AGREEMENT FOR SUPPORTS SERVICES ASSOCIATED WITH METRO’S CONSTRUCTION PROJECTS

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to execute the Utility Cooperative Agreement (UCA) between Metro (Authority) and XO Communications.

 

Issue

ISSUE

 

As the Purple Line Extension Project (PLE) moves forward, the team has identified XO communication systems within the alignment that require utility relocation and or general utility support from the proposed decking system. This is the Authority’s first interaction with XO Communication. Therefore in order to move forward with the relocations and general utility support coordination, a Utility Cooperative Agreement (UCA) must be set in place between the Authority and XO Communication in order to memorialize roles and responsibilities. This UCA shall also be prepared in a manner that would accommodate any future Metro Project that may require services from XO Communication in order to support those future projects.

 

Discussion

DISCUSSION

 

As technology advances, new communication providers are constantly installing new infrastructure within Metro proposed Project areas. Such as in the case of XO Communication. XO Communication is a relatively new fiber and communication company that now services L.A. County as well as the unincorporated counties.  Being that they are relatively new, and no other UCA has been executed by both parties, this would be the first UCA executed that would allow both parties to collectively work together to support general utility relocation and coordination efforts. The general intent of the UCA would be to cover the current ongoing Projects, starting with PLE, as well as future Metro Projects for many years to come.

 

This UCA describes the roles, responsibilities, and obligations of both parties and specifies the procedures which the Authority and XO Communication will follow for elements associated with the supports services associated with all of Metro’s projects. Such elements include general coordination, providing as builts, relocating utilities, preparation of designs, streamline processes, meeting accommodations, permitting, construction support services, reimbursements, invoicing, and other general tasks in support of Metro’s construction of projects. The Authority and XO Communication agree that each will cooperate with the other in all activities covered by the UCA. Work performed by XO Communication under this UCA shall be per the work orders to be issued by the Authority on a yearly basis.

 

Financial_Impact

FINANCIAL IMPACT

 

Work Orders will be issued to XO Communications on an annual basis similar to contract task orders.  Work orders for said Authority commitments created within the UCA parameters shall only be issued by funded projects and must be within each of the project’s respective Fiscal Year or Life of Project (LOP) budgets. These projects will largely be comprised of the Measure R/M projects but can be utilized across all Metro capital projects.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to execute this UCA, however not executing this UCA would not solidify each of the parties’ roles and responsibilities and would require Metro to follow standard over the counter processes and therefore not benefit from streamlined processes, and other administration benefits identified within the UCA.  All of which are essential elements from a successful project standpoint.

 

Attachments

ATTACHMENTS

 

Attachment A - Utility Cooperative Agreement; XO Communication

 

Prepared_by

Prepared by:                      Eduardo Cervantes, Senior Director; 213-922-7255.

                                                                Androush Danielians, Deputy Executive Officer; 213-922-7598

 

Reviewed_By

Reviewed by:                      Richard Clarke, Chief Program Management Officer; 213-922-7557