File #: 2018-0016   
Type: Agreement Status: Agenda Ready
File created: 1/29/2018 In control: Construction Committee
On agenda: 3/15/2018 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute the Utility Cooperative Agreement (UCA) between Metro (Authority) and Enwave Los Angeles ("Enwave") for support services associated with Metro's construction projects.
Sponsors: Construction Committee
Indexes: Construction, Construction Support, Metro Purple Line, Metro Rail D Line, Project, Utility Cooperative Agreement, Westside Subway Extension/Purple Line Extension Phase 2
Attachments: 1. Attachment A - Utility Cooperative Agreement
Related files: 2018-0154

Meeting_Body

CONSTRUCTION COMMITTEE

MARCH 15, 2018

 

Subject

SUBJECT:                     ENWAVE LOS ANGELES UTILITY COOPERATIVE

AGREEMENT

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to execute the Utility Cooperative Agreement (UCA) between Metro (Authority) and Enwave Los Angeles (“Enwave”) for support services associated with Metro’s construction projects.

 

Issue

ISSUE

 

As the Purple Line Extension Section 2 Project (PLE) moves forward, the team has identified Enwave systems within the alignment that require general utility coordination and utility support scope. This is the Authority’s first interaction with Enwave. Therefore in order to move forward with the general scope, a Utility Cooperative Agreement (UCA) must be set in place between the Authority and Enwave in order to memorialize roles and responsibilities. This UCA shall also be prepared in a manner that would accommodate any future Metro Project that may require services from Enwave in order to support those future projects.

 

Discussion

DISCUSSION

 

As technology advances, new utility providers are constantly installing new infrastructure within Metro proposed Project areas. Such as in the case of Enwave. Enwave is a relatively a new utility company that now services LA County as well as the unincorporated counties.  Being that they are relatively new, and no other UCA has been executed between both parties, this would be the first UCA executed that would allow both parties to collectively work together to support general utility relocation and coordination efforts. The general intent of the UCA would be to cover the current ongoing Projects as well as future Metro Projects for many years to come.

 

This UCA describes the roles, responsibilities, and obligations of both parties and specifies the procedures which the Authority and Enwave will follow for elements associated with the support services associated with all of Metro’s projects. Such elements include general coordination, providing as builts, relocating utilities, preparation of designs, streamline processes, meeting accommodations, permitting, construction support services, reimbursements, invoicing, and other general tasks in support of Metro’s construction of projects. The Authority and Enwave agree that each will cooperate with the other in all activities covered by the UCA. Work performed by Enwave under this UCA shall be per the work orders to be issued by the Authority on a yearly basis.

 

Financial_Impact

FINANCIAL IMPACT

 

Work Orders will be issued to Enwave on an annual basis similar to contract task orders.  Work orders for said Authority commitments created within the UCA parameters shall only be issued by funded projects and must be within each of the project’s respective Fiscal Year or Life of Project (LOP) budgets. These projects will largely be comprised of the Measure R/M projects but can be utilized across all Metro capital projects.

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may choose not to execute this UCA, however not executing this UCA would not solidify each of the parties’ roles and responsibilities and would require Metro to follow standard over the counter processes and therefore not benefit from streamlined processes, and other administration benefits identified within the UCA.  All of which are essential elements from a successful project standpoint.

 

Attachments

ATTACHMENTS

 

Attachment A - Utility Cooperative Agreement; Enwave

 

Prepared_by

Prepared by:                      

Eduardo Cervantes, Senior Director; 213-922-7255

Androush Danielians, Deputy Executive Officer; 213-922-7598

 

Reviewed_By

Reviewed by:                      

Richard F. Clarke, Chief Program Management Officer; 213-922-7557