File #: 2018-0352   
Type: Contract Status: Agenda Ready
File created: 5/30/2018 In control: Board of Directors - Regular Board Meeting
On agenda: 6/28/2018 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute: A. Modification No. 2 to Contract No. AE5999300 with WSP USA Inc. for technical services for the evaluation of the two northern alignments in the Draft Environmental Impact Statement/Environmental Impact Report in the amount of $2,760,752, increasing the total contract value to $12,405,244; and B. Modification No. 1 to Contract No. PS2492300 with Arellano Associates for outreach support for the augmented Community Participation Program as part of the evaluation of the two northern alignments in the Draft EIS/EIR in the amount of $429,310, increasing the total contract value to $922,203.
Sponsors: Board of Directors - Regular Board Meeting
Indexes: Alignment, Budgeting, Contractors, Contracts, Downtown Los Angeles, Environmental Impact Report, Environmental impact statements, Light rail transit, Los Angeles Union Station, Metro Rail A Line, Outreach, Port of Long Beach, Port of Los Angeles, Procurement, Project, West Santa Ana Branch Corridor - Administration (Project), West Santa Ana Branch Transit Corridor, West Santa Ana Branch Transit Corridor (WSAB) Project
Attachments: 1. Attachment A-1 - Procurement Summary AE5999300, 2. Attachment A-2 - Procurement Summary PS2492300, 3. Attachment B-1 - Contract Modification Change Order Log AE5999300, 4. Attachment B-2 - Contract Modification Change Order Log PS2492300, 5. Attachment C-1 - DEOD Summary for A-1, 6. Attachment C-2 - DEOD Summary for A-2, 7. Staff Report
Related files: 2018-0072, 2018-0442
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
REGULAR BOARD MEETING
JUNE 28, 2018

Subject
SUBJECT: WEST SANTA ANA BRANCH TRANSIT CORRIDOR

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
AUTHORIZE the Chief Executive Officer to execute:

A. Modification No. 2 to Contract No. AE5999300 with WSP USA Inc. for technical services for the evaluation of the two northern alignments in the Draft Environmental Impact Statement/Environmental Impact Report in the amount of $2,760,752, increasing the total contract value to $12,405,244; and

B. Modification No. 1 to Contract No. PS2492300 with Arellano Associates for outreach support for the augmented Community Participation Program as part of the evaluation of the two northern alignments in the Draft EIS/EIR in the amount of $429,310, increasing the total contract value to $922,203.

Issue
ISSUE

Board action is requested in order to execute the contract modifications for technical services and outreach support to proceed with the environmental analysis and remain on schedule per the Measure M groundbreaking date of Fiscal Year (FY) 2022.

Background
BACKGROUND

The WSAB Project is a proposed light rail transit (LRT) line that would extend approximately 20 miles from downtown Los Angeles through southeast Los Angeles County (LA County). South of downtown Los Angeles, a single alignment has been identified following existing right-of-way parallel to the Blue Line owned by Union Pacific, then along Randolph Avenue in the City of Huntington Park using Metro owned right-of-way (ROW), then following the San Pedro Subdivision Branch (owned by Port of Los Angeles and Port of Long Beach), to the eight-mile, Metro-owned, abandoned Pacific Electric ROW to the southern terminus in the City of Artesia. The WSAB Project would traverse a highly populated area, with high numbers of low-income and heavily transit-dependent residents. A primary goal of the Project is to improve mobility by connecting the communities of southeast LA Cou...