File #: 2018-0383   
Type: Motion / Motion Response Status: Agenda Ready
File created: 6/6/2018 In control: Ad Hoc Congestion, Highway and Roads Committee
On agenda: 11/14/2018 Final action:
Title: RECEIVE AND FILE report on the history and status of the I-5 North capacity enhancements construction projects (Project) and enhancing Metro and Caltrans coordination to deliver the remaining segments in response to Board Motion 2018-0115 (Attachment A).
Sponsors: Ad Hoc Congestion, Highway and Roads Committee
Indexes: Arroyo Verdugo subregion, Burbank, Construction, Contractors, Contracts, High occupancy vehicle lanes, I-5, I-5 North County Capacity Enhancements, Jacquelyn Dupont-Walker, Mitigation, Motion / Motion Response, Project, Project Status Report, San Fernando Valley Service Sector, San Fernando Valley subregion, Southern California Highways, SR-1, SR-118, SR-134, SR-170
Attachments: 1. Attachment A - Board Motion- File # 2018-0115, 2. Presentation
Related files: 2018-0115
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.



Meeting_Body
AD HOC CONGESTION, HIGHWAY AND ROADS COMMITTEE
NOVEMBER 14, 2018
Subject
SUBJECT: I-5 NORTH CAPACITY ENHANCEMENTS UPDATE

Action
ACTION: RECEIVE AND FILE

Heading
RECOMMENDATION

Title
RECEIVE AND FILE report on the history and status of the I-5 North capacity enhancements construction projects (Project) and enhancing Metro and Caltrans coordination to deliver the remaining segments in response to Board Motion 2018-0115 (Attachment A).

Issue
ISSUE

At the May 2018 Regular Board Meeting, Director Dupont-Walker requested Metro staff to provide a status report on the Project and Metro-Caltrans collaboration to effectively complete the Project.

Background
BACKGROUND

The Project is a mega-project, which includes construction of High Occupancy Vehicle (HOV) Lanes and pertinent improvements between State Route 134 (SR-134) in Glendale and State Route 118 (SR-118) in Pacoima area in four segments:

Segment 1: SR-118 to SR-170
Segment 2: SR-170 to Buena Vista St.
Segment 3: Buena Vista St. to Magnolia Blvd.
Segment 4: Magnolia Blvd. to SR-134

Caltrans designed and is managing construction of the Project. Segments 1 & 2 are complete and opened to traffic. Segments 3 & 4 are currently in construction. Table 1 shows the history and status of the four segments of the Project.








Table 1: Project History and Current Status
Project Limits
Award Date
Original Scheduled Completion Date
Actual/Anticipated Completion Date
% Complete to Date
SR-118 to SR-170 (Segment 1)
May 2010
Jun. 2015
Jul. 2016
100%
SR-170 to Buena Vista St. (Segment 2)
Oct. 2010
May 2014
Dec.2015
100%
Buena Vista St. to Magnolia Blvd.
(Segment 3)
Nov. 2012
Sep. 2017
TBD (Apr. 2022)
70%
Magnolia Blvd. to SR-134 (Segment 4)
Dec. 2010
Aug. 2014
TBD (Mar. 2020)
83%

Discussion
DISCUSSION

The Project has experienced schedule delays and cost increases. A number of challenges occurred during the construction of the Project including survey discrepancies, desi...