File #: 2018-0624   
Type: Budget Status: Agenda Ready
File created: 9/18/2018 In control: Crenshaw Project Corporation
On agenda: 12/6/2018 Final action:
Title: APPROVE the Fiscal Year 2018-2019 (FY19) budget in the amount of $36,406 for the operation and administration of the Crenshaw Project Corporation (CPC).
Sponsors: Crenshaw Project Corporation
Indexes: Budget, Budgeting, Crenshaw/LAX Transit Corridor Project, Los Angeles International Airport, Metro Crenshaw Line, Metro Exposition Line, Metro Green Line, Metro Rail C Line, Metro Rail E Line, Metro Rail K Line, Payment, Project, Transportation Infrastructure Finance and Innovation Act of 1998
Attachments: 1. Attachment A - Proposed FY19 Budget Summary
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.

Meeting_Body

Crenshaw Project Corporation

                     

 

One Gateway Plaza

Los Angeles, CA 90012

 

CRENSHAW PROJECT CORPORATION BOARD MEETING

DECEMBER 6, 2018

 

Subject

SUBJECT:                     CRENSHAW PROJECT CORPORATION FISCAL YEAR BUDGET

 

Action

ACTION:                     APPROVE RECOMMENDATION

 

Heading

RECOMMENDATION

 

Title

APPROVE the Fiscal Year 2018-2019 (FY19) budget in the amount of $36,406 for the operation and administration of the Crenshaw Project Corporation (CPC).

 

Issue

ISSUE

 

CPC Bylaws, Article 5.2(b), require preparation of an annual budget for administrative support.  A summary of the proposed budget is provided as Attachment A.

 

Background

BACKGROUND

 

The CPC was formed on March 23, 2012 to act as the Transportation Infrastructure Finance and Innovation Act (TIFIA) Loan conduit borrower and the Transportation Investment Generating Economic Recovery (TIGER) II TIFIA Payment grant sub-recipient for the Crenshaw/LAX Transit Corridor Project (Crenshaw/LAX)). 

 

Discussion

DISCUSSION

 

As of August 25, 2016, the CPC has drawn the entire $545.9 million TIFIA loan available to the Crenshaw/LAX project. All loan disbursements have been advanced to Metro for the purpose of reimbursing the agency for eligible Crenshaw/LAX Project expenses. In FY18, the CPC paid $23,397 in expenses for trustee services and loan administration fees as well as other charges.  The CPC was reimbursed for these expenditures by Metro.

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

There is no safety impact related to this action.

 

Financial_Impact

FINANCIAL IMPACT

 

The CPC Annual Budget was funded in Metro’s adopted FY19 budget in various cost centers for services related to debt management.

 

Next_Steps

NEXT STEPS

 

Staff will monitor actual payments to ensure CPC expenses are fiscally responsible.

 

Attachments

ATTACHMENTS

 

Attachment A - Proposed FY19 Budget Summary

 

Prepared_by

Prepared by:                      Susan Cariasa-Ginsberg, Manager, Admin. & Financial Services, 213-922-6162

                     LuAnne E. Schurtz, DEO Finance, Treasury, 213-922-4143

                     Donna Mills, Treasurer, Treasury, 213-922-4047

 

Reviewed_By

Reviewed by:                      Nalini Ahuja, Chief Financial Officer, (213) 922-3088