Meeting_Body
AD HOC CONGESTION, HIGHWAY, AND ROADS COMMITTEE
JUNE 19, 2019
Subject
SUBJECT: MEASURE R HIGHWAY SUBREGIONAL PROGRAM SEMI-ANNUAL UPDATE
Action
ACTION: APPROVE RECOMMENDATIONS
Heading
RECOMMENDATION
Title
CONSIDER:
A. APPROVING $8,384,000 dollars of additional programming within the capacity of the Measure R Highway Subregional Programs and funding changes via the updated project list as shown in Attachment A for:
* Highway Operational Improvements in Arroyo Verdugo
* Highway Operational Improvement in Las Virgenes Malibu
* I-405, I-110, I-105 and SR-91 Ramp and Interchange Improvements (South Bay)
* I-605 Corridor "Hot Spots" Interchange Improvements in Gateway Cities
* I-710 South and/or Early Action Projects in Gateway Cities
B. DEOBLIGATING $26,993,000 dollars of previously approved Measure R Highway Subregional Program funds for re-allocation at the request of project sponsors;
C. AUTHORIZING the CEO or his designee to negotiate and execute all necessary agreements for the approved projects.
Issue
ISSUE
The Measure R Highway Subregional Program update allows the Metro Highway Program and each subregion or lead agency to revise delivery priorities and amend project budgets for the implementation of the Measure R Highway subregional projects. The attached updated project lists include projects which have received prior Board approval, as well as proposed changes related to schedules, scope, funding allocation and the addition or removal of projects. The Board's approval is required as the updated project lists serve as the basis for Metro to enter into agreements with the respective implementing agencies.
Background
BACKGROUND
Lines 31, 32, 33, 35, 37, 38 of the 2008 Measure R Expenditure Plan addresses Highway Operational Improvement subfunds. The Highway Department in Program Management develops and environmentally clears highway projects with these subfunds and also manages grants to jurisdictions and coordinates with ea...