File #: 2019-0557   
Type: Contract Status: Agenda Ready
File created: 9/18/2019 In control: Planning and Programming Committee
On agenda: 10/16/2019 Final action:
Title: AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 12 to Contract No. AE469080015383 with CH2M Hill, Inc. (now Jacobs Engineering) for additional design services in the firm-fixed price amount of $923,203 increasing the Total Contract Value from $33,889,867 to $34,813,070.
Sponsors: Planning and Programming Committee
Indexes: Board approved Contract, Budgeting, Contracts, Easements, Federal Highway Administration, High occupancy vehicle lanes, I-5, I-5 N Enhance Sr14/Kern Cnty (Project), Procurement, Project, Safety, Southern California Highways, SR-14, Temporary Construction Easement, Vehicle occupancy
Attachments: 1. Attachment A - Procurement Summary, 2. Attachment B - ContractModifcaiton, 3. Attachment C - DEOD Summary

Meeting_Body

PLANNING AND PROGRAMMING COMMITTEE

OCTOBER 16, 2019

 

Subject

SUBJECT:                     I-5 NORTH HOV LANES CONTRACT

 

Action

ACTION:                     APPROVE CONTRACT MODIFICATIONS

 

Heading

RECOMMENDATION

 

Title

AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 12 to Contract No. AE469080015383 with CH2M Hill, Inc. (now Jacobs Engineering) for additional design services in the firm-fixed price amount of $923,203 increasing the Total Contract Value from $33,889,867 to $34,813,070.

 

Issue

ISSUE

 

This modification to contract No. AE469080015383 is required to complete the Plans, Specifications and Estimate (PS&E) of the I-5 North High Occupancy Vehicle Lanes Project from SR-14 to Parker Road (Project).  The additional work is needed to address changes in the baseline conditions of the corridor and Caltrans’ changes in design requirements that were not anticipated in the original scope of work.  The additional scope includes, but is not limited to:

                     additional roadway improvements including overhead sign work, changing the guardrail systems due to a change in Caltrans Design Standards, and changes to the Magic Mountain Parkway NB off-ramp improvements due to a hotel redevelopment that started while the Project design was in progress;

                     design changes due to changes in existing conditions as a result of the on-going Caltrans pavement rehabilitation project;

                     design updates due to the release of Caltrans 2018 Revised Standard Plans;

                     43 additional non-standard specifications exceeding the original Scope of Work assumptions;

                     incorporating additional right of way requirements, including appraisal maps, legal descriptions, and plats for the Temporary Construction Easements (TCEs) and Permanent Easements; and

                     additional landscape work based on Caltrans requirement to locate trees in the field and the permit condition of a 5-year plant establishment and monitoring period. 

 

Background

BACKGROUND

 

The 13.9-mile project on I-5 from SR-14 to Parker Road was identified for capacity enhancements to improve the operations and safety of the corridor, facilitate the movement of freight and people and to reduce existing and future forecasted congestion due to expected growth in the area.

 

The proposed improvements include the addition of one High Occupancy Vehicle (HOV) lane in each direction to improve mobility; extension of truck lanes from Calgrove Blvd. to South of Weldon Canyon in the southbound direction (2.23 miles) and from the Gavin Canyon undercrossing to Calgrove Blvd. in the northbound direction (0.98 miles); auxiliary lanes at various locations along the corridor (2.5 miles); widening of the existing roadway and 7 bridges including the Gavin Canyon Undercrossing, Calgrove Boulevard Undercrossing, Butte Canyon Bridge, Magic Mountain Parkway Undercrossing, Santa Clara Overhead, Rye Canyon Undercrossing, and Castaic Creek Bridge; and the replacement of the Weldon Canyon bridge to accommodate the proposed freeway widening. 

 

The original contract for final design was approved by the Board on April 20, 2016. 

 

Discussion

DISCUSSION

 

Additional design work/changes required by Caltrans, changes in Caltrans standards, and Hazardous Waste analysis led to additional work not anticipated/included under the original contract. All projects on the State Highway System initiated by Metro need to comply with Caltrans requirements. Hence, the escalation in the value of the current contract that requires Board approval.

 

Considerations

 

Determination_Of_Safety_Impact

DETERMINATION OF SAFETY IMPACT

 

The proposed action has no known adverse impact on the safety of Metro’s patrons, employees or users of the facility.  Caltrans highway safety standards are followed in the design of the proposed improvements and exceptions to the standards will be incorporated in accordance with Caltrans and Federal Highway Administration (FHWA) procedures.

 

Financial_Impact

FINANCIAL IMPACT

 

For FY20, $15,862,673 has been budgeted in Highway Program Cost Center 4730, in the I-5 North Enhancements from SR-14 to Parker Road Project 460313, Task 5.5.101, in Professional Services Account 50316.

 

Impact to Budget

 

The sources of funds for this project are Measure R Highway Capital (20%) and Measure M (17%) Funds.  These funds are not eligible for bus and rail operations and/or capital expenditures.

 

Implementation_of_Strategic_Plan_Goals

IMPLEMENTATION OF STRATEGIC PLAN GOALS

 

The recommendation supports Strategic Plan Goal No. 1, to provide high quality mobility options that enable people to spend less time traveling.  New HOV Lanes add capacity to the I-5 and provide an incentive for carpool formation.

 

 

 

Alternatives_Considered

ALTERNATIVES CONSIDERED

 

The Board may elect not to approve the staff’s recommendation.  This option is not recommended.  Without the design changes, final PS&E would not be approved, and the project would not advance to construction.

 

Next_Steps

NEXT STEPS

 

Upon approval by the Board, staff will execute Contract Modification No. 12 to Contract No. AE469080015383 with CH2M Hill, Inc. (now Jacobs Engineering).

 

Attachments

ATTACHMENTS

 

Attachment A - Procurement Summary

Attachment B - Contract Modification/Change Order Log

Attachment C - DEOD Summary

 

 

Prepared_by

Prepared by:                      Carlos J. Montez, Sr. Director, Program Management, (213) 418-3241

Abdollah Ansari, Senior Executive Officer, (213) 922-4781

Bryan Pennington, Deputy Chief Programming Management Officer, (213) 922-7449

 

Reviewed_By

Reviewed by:                      Richard F. Clarke, Chief Program Management Officer, (213) 922-7557

Debra Avila, Chief Vendor/Contract Management Officer (213) 418-3051