File #: 2020-0232   
Type: Program Status: Agenda Ready
File created: 3/19/2020 In control: Planning and Programming Committee
On agenda: 4/15/2020 Final action:
Title: CONSIDER: A. APPROVING: 1. Deobligation of $4,226,964 previously approved Measure M Multi-Year Subregional Program (MSP) - Active Transportation Program, for re-allocation at the request of project sponsors, as shown in Attachment A; 2. Programming of additional $12,750,000 within the capacity of Measure M MSP - Transit Program, as shown in Attachment B; and 3. Inter-program borrowing and programming of additional $4,350,143 from the Subregion's Measure M MSP - Active Transportation and Transit Programs to the Highway Efficiency Program, as shown in Attachment C; and B. AUTHORIZING the Chief Executive Officer or his designee to negotiate and execute all necessary agreements and/or amendments for approved projects.
Sponsors: Planning and Programming Committee
Indexes: Active Transporation, Transit And Tech Program - Expenditure Plan Line Item 56 (Project), Active Transportation Program, Agreements, Bicycling, Budgeting, Construction, Deobligation, Guidelines, Highway Efficiency Program, Highway Efficiency Program (North County) (Project), Joint Powers Agreement, Lake Los Angeles, Lancaster, Measure M, Measure M Multi-Year Subregional Program, Measure R, Metrolink, Metrolink Antelope Valley Line, Nonmotorized transportation, North Los Angeles County subregion, North Los Angeles County Transportation Coalition, Outreach, Palmdale, Pedestrians, Plan, Program, Project, Ridesourcing, Santa Clarita, SR-138, SR-14, Subsidies, Valencia
Attachments: 1. Attachment A - Active Transportation Project List, 2. Attachment B - Transit Program Project List, 3. Attachment C - Highway Efficiency Program Project List
Related files: 2020-0132
Date Action ByActionResultAction DetailsMeeting DetailsAudio
No records to display.
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
APRIL 15, 2020

Subject
SUBJECT: MEASURE M MULTI-YEAR SUBREGIONAL PROGRAM ANNUAL UPDATE - NORTH COUNTY SUBREGION

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
CONSIDER:

A. APPROVING:

1. Deobligation of $4,226,964 previously approved Measure M Multi-Year Subregional Program (MSP) - Active Transportation Program, for re-allocation at the request of project sponsors, as shown in Attachment A;

2. Programming of additional $12,750,000 within the capacity of Measure M MSP - Transit Program, as shown in Attachment B; and

3. Inter-program borrowing and programming of additional $4,350,143 from the Subregion's Measure M MSP - Active Transportation and Transit Programs to the Highway Efficiency Program, as shown in Attachment C; and

B. AUTHORIZING the Chief Executive Officer or his designee to negotiate and execute all necessary agreements and/or amendments for approved projects.

Issue
ISSUE

Measure M MSPs are included in the Measure M Expenditure Plan. All MSP funds are limited to capital projects. The annual update approves additional eligible projects for funding and allows the North County Subregion and implementing agencies to revise scope of work, schedule, amend project budgets as well as removal of projects. This update includes changes to projects which have received Board approval and funding allocation for new projects. Funds are programmed through Fiscal Year (FY) 2022-23. The Board's approval is required to program additional funds and the updated project lists which serve as the basis for Metro to enter into agreements and/or amendments with the respective implementing agencies.

Discussion
DISCUSSION

In February 2019, the Metro Board of Directors approved North County Subregion's first MSP Five-Year Plan and programmed funds in: 1) Measure M MSP - Active Transportation Program (expenditure line 52); 2) Measure M MSP - Transit Program (expenditure line 64); and 3)...

Click here for full text