File #: 2020-0334   
Type: Plan Status: Passed
File created: 5/5/2020 In control: Planning and Programming Committee
On agenda: 6/17/2020 Final action: 6/25/2020
Title: ?CONSIDER: A. APPROVING the Measure R Ordinance Proposed Amendment Language (Attachment A); and, B. ADOPTING the Resolution Notifying the State Legislature of the Amendment (Attachment C).
Sponsors: Planning and Programming Committee
Indexes: Budgeting, Capital Project, Capital Project Funds, Construction, Council Of Governments, Debt, Funding plan, Measure M, Measure R, Plan, Program, Project, Resolution, South Bay Cities subregion, South Bay Subregion Council of Governments, Transfers
Attachments: 1. Attachment A - Expenditure Plan Mark-Up.pdf, 2. Attachment B - South Bay Highway Program Unfunded Construction Projects.pdf, 3. Attachment C - Resolution Notifying the State Legislature of the Amendment.pdf
Related files: 2020-0418, 2020-0447
Meeting_Body
PLANNING AND PROGRAMMING COMMITTEE
JUNE 17, 2020
EXECUTIVE MANAGEMENT COMMITTEE
JUNE 18, 2020

Subject
SUBJECT: MEASURE R AMENDMENT LANGUAGE

Action
ACTION: APPROVE RECOMMENDATIONS

Heading
RECOMMENDATION

Title
?CONSIDER:

A. APPROVING the Measure R Ordinance Proposed Amendment Language (Attachment A); and,

B. ADOPTING the Resolution Notifying the State Legislature of the Amendment (Attachment C).

Issue
ISSUE

This Board item presents proposed amendments and changes to the Measure R Ordinance (the Ordinance) to allow transfers between the highway and transit subfunds, and adds a project requested by a subregion. Board approval of this item will allow the amendment language to be presented at a public hearing, noticed to the required governing bodies, and reviewed by the Measure R Oversight Committee, which are steps required under the Ordinance prior to Board adoption of the amendment. The Public Utilities Code also requires that Metro adopt a resolution notifying the state legislature of the amendment.

Background
BACKGROUND

The Ordinance identifies the allowable uses for the 0.5% countywide sales tax that funds Metro capital projects and transit operations. The Ordinance created both transit and highway capital subfunds that receive a percentage of the Measure R sales tax revenue and fund the capital projects listed on the Expenditure Plan (Attachment A of the Ordinance).

The Measure R Ordinance can be amended upon two-thirds vote of the Board. However, any amendment to provide for a transfer of moneys between the highway and transit subfunds can only occur every ten years, beginning 2020.

In anticipation of the first allowable transfer amendment, staff notified the Board in November 2019 and began a process to inform and reach out to stakeholders including Metro staff, Board staff, subregional councils, Policy Advisory Council, and the public at-large.

Staff distributed an information letter to all known interested parti...

Click here for full text