Meeting_Body
CONSTRUCTION COMMITTEE
AUGUST 20, 2020
Subject
SUBJECT: DIVISION 11 AND 22 HVAC AND ROOF REPLACEMENT
Action
ACTION: APPROVE CONTRACT MODIFICATION
Heading
RECOMMENDATION
Title
AUTHORIZE the Chief Executive Officer to execute Contract Modification No. 3 to Contract No. C56872C1142 with Archico Design Build Inc. to provide Heating, Ventilation and Air Conditioning (HVAC) replacement and additional roofing replacement and increase the contract price by $1,820,450.00 from $6,570,294.00 to $8,390,744.00.
Issue
ISSUE
Archico Design Build Inc. is contracted to provide roof replacement at Metro Operating Divisions 11 and 22. During the project, a need for the replacement of the HVAC equipment at these locations was identified. Due to Archico Design Build Inc. removing the existing HVAC equipment as part of the scope of work for the roof replacement, it has been identified that replacement equipment can be added as part of the new scope of work. Maintenance of Way Engineering seeks board approval to modify the current contract.
Background
BACKGROUND
In May 2019, Metro awarded Contract No. C56872C1142 to Archico Design Build Inc. to perform a complete design, roofing system tear off and replacement at the Division 11 Ancillary Shop and Vehicle Shop Buildings and the Division 22 Maintenance Shop Building.
In January 2020, the HVAC equipment at Divisions 11 and 22 were identified to be at their end-of-Life, beyond repair, having significant environmental risks and leaking significant amounts of non-compliant refrigerants when the units fail, a violation that can result in fines. Due to Archico Design Build Inc. removing the existing HVAC equipment as part of the roof replacement scope, it has been determined that Archico Design Build Inc. could replace the equipment with new energy efficient equipment.
Discussion
DISCUSSION
Under this contract, Archico Design Build Inc. provides design, construction and project management services. The...