Subject
SUBJECT: REGIONAL CONNECTOR SERVICE PLAN
Action
ACTION: APPROVE RECOMMENDATION
Heading
RECOMMENDATION
Title
APPROVE Alternative A (Long Beach - APU/Citrus College and Santa Monica - Atlantic) as the opening day service plan for Regional Connector.
Issue
ISSUE
The Regional Connector is anticipated to open in the Summer of 2022. This project will connect the A Line (Blue), E Line (Expo) and L Line (Gold) into one integrated light rail network with all trains serving three new stations through downtown LA. The service plan described in the Locally Preferred Alternative (LPA) of the 2012 Final Environmental Impact Statement/Environmental Impact Report (EIS/EIR) described trains routed through downtown LA in a North/South and East/West configuration connecting Long Beach to APU/Citrus College and beyond and Santa Monica to Atlantic and beyond. This service plan has been referenced in public outreach and engagement through the EIS/EIR stage of the project as well as during construction. The Board action recommended in this report seeks to validate and approve the LPA as the service plan for operations starting opening day of the Regional Connector.
Discussion
DISCUSSION
The Regional Connector Transit Project is a 1.9 mile Light Rail Transit extension that will connect the A Line (Blue) and E Line (Expo) with the L Line (Gold) through downtown LA. By connecting the three rail lines together, the L Line (Gold) would be severed at Little Tokyo Station. However, all lines will run through downtown LA and serve three new stations at:
* Little Tokyo/Arts District Station - 1st St/Central Av
* Historic Broadway Station - 2nd St/Broadway
* Grand Av Arts/Bunker Hill Station - 2nd Pl/Hope St
In addition, Regional Connector provides the opportunity to connect the A Line (Blue) and E Line (Expo) with L Line (Gold) giving customers direct service through downtown LA. Th...
Click here for full text